Re: Changing Resource % mid project.
- From: "Steve House [Project MVP]" <sjhouse.remove.this@xxxxxxxxxxxxxxxxxxx>
- Date: Tue, 24 May 2005 16:50:36 -0400
There are several things to think about here.
First of all, you need to make sure it is even *possible* to arbitrarily change the resource allocation like you want to show in the plan. The nature of the work itself has to enter the picture.
You mention that these "tasks" involve waiting for responses. IMHO, those are not tasks at all and should NOT be entered as such in the plan. A task is, by definition, an activity, usually physical, producing a deliverable. Waiting is again by definition, non-activity. If I submit a proposal and have to wait two weeks for a response, the wait itself is not a task requiring my presence and effort. Instead it is a two week lag time in the link leading from the task "Submit Proposal" to the milestone "Approval Received" requiring no attention or effort on my part and I'm completely free to do other things during that time period. If you show it as a task assigned to a resource it means work is being performed on it consuming the resource's energy and the cost of that work is included in your budget.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
"SteveA" <steveahlcrona@xxxxxxxxxxxxx> wrote in message news:1116510623.033090.232260@xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
Thanks for the response.
Both tasks involve waiting for responses and following up on responses from resources outside of the company. There will be down time, and if the tasks were done in sequence the resource would be under allocated.
Thanks.
v/r SteveA.
.
- References:
- Changing Resource % mid project.
- From: SteveA
- RE: Changing Resource % mid project.
- From: SpiroT
- Re: Changing Resource % mid project.
- From: SteveA
- Re: Changing Resource % mid project.
- From: Jan De Messemaeker
- Re: Changing Resource % mid project.
- From: SteveA
- Changing Resource % mid project.
- Prev by Date: Re: Change the start date and move all tasks
- Next by Date: RE: Leveling makes 23hr of work take 44 years!
- Previous by thread: Re: Changing Resource % mid project.
- Next by thread: Web Based Schedules
- Index(es):
Relevant Pages
|