Re: multi-level linking

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Julie,

I use many "production" grade sub-plans (15 - 20) that are inserted into a
Master plan, and wouldn't be surprised if there were several hundred links
between these sub-plans. There are sub-sub-plans, also. The only difficulty I
have occaisionally is when one of the Project Managers or myself (I only
maintain the Master) are not careful and create a "circular relationship"
when linking. I find these a bit harder to track down at times than if it
happened within a single project plan (although the gray hair I pull out is
not considered a total loss at this point :).

--
Don L.


"John" wrote:

> In article <eGkb1kLUFHA.584@xxxxxxxxxxxxxxxxxxxx>,
> "JulieD" <JulieD@xxxxxxxxxxxxxxxxxxxxx> wrote:
>
> > hi all
> >
> > was discussing linking project files or creating larger projects today and
> > was wondering what your experience has been with mult-level linking e.g.
> >
> > lowest level: "blocks" - approx 100-150 tasks
> > next level: "countries" - consisting of between 1 & 5 "blocks"
> > next level: "combined" - consisting of three "countries"
> >
> > all "blocks" using a combined resource pool.
> >
> > My feeling is that this is possibly "asking for trouble" and that it would
> > be best to dispense with the "lowest level" and have the blocks as outline
> > level 1 in the "countries" project file and then just combine the countries
> > into the "combined" one - but are interested in other's options and
> > comments.
>
> Julie,
> I'm not sure if this relates to your question but the main test file I
> use for answering newsgroup posts and developing macros is a multi-level
> master file. It consists of a master file which also holds the resource
> pool. Inserted into the master are two subprojects (level 1), one of
> which has a subproject (level 2) which has a subproject (level 3). This
> particular setup does not have external links between files - not
> because there is a problem necessarily - I just never had the need to
> set any up. Off hand, I don't foresee any problems if external links
> were added to the mix. The same care and diligence would apply to any
> file structure with external links.
>
> Bottom line, I have been using this master test file for a couple of
> years with no issues.
>
> Hope this helps.
> John
> Project MVP
>
.



Relevant Pages

  • Re: Corrupted Project 2002 master plan
    ... After looking at the master project, there are some links on summary lines. ... lead to corruption. ... With respect to converting the dynamic master with separate subprojects, ... opening the master plan recently, I received one of the typical Microsoft ...
    (microsoft.public.project)
  • Re: Master Project Data Inconsistencies
    ... I appreciate that the data is not held in the master plan and I ... understand that it is updated on expanding/opening the inserted ... Contract inserted plan A - inserted plan sub totals remain accurate, ...
    (microsoft.public.project)
  • Re: Master Project Data Inconsistencies
    ... Sorry Graham, try as I might, I cannot get my master to give me different data. ... I appreciate that the data is not held in the master plan and I ... understand that it is updated on expanding/opening the inserted ... Contract inserted plan A - inserted plan sub totals remain accurate, ...
    (microsoft.public.project)
  • Re: Master Plan
    ... the master from the individual plans and the resource pool, ... the master plan seem to be reflected in the other plans, ... you also have a resource pool file, ... If you have a resource pool, open each sharer file and then the pool ...
    (microsoft.public.project)
  • Re: Master Plan
    ... the master from the individual plans and the resource pool, ... the master plan seem to be reflected in the other plans, ... you also have a resource pool file, ... If you have a resource pool, open each sharer file and then the pool ...
    (microsoft.public.project)