Re: Hod do I insert multiple sub projects?



Thanks for the help. I understand what you are proposing, and as I think
about it more, I realize why I wanted to use copies of the same project - so
that I can change the tasks in one spot, it changes it across all of the
sites (whether I add/delete a task or change the duration of a task). Is
there a way to do this? Of course in an ideal world, this wouldn't be
necessary, but in the world of "you can do that in x minus y days, what's
that new schedule look like" this could save me a lot of time re-working
project.

Thanks,
Greg

"Steve House [MVP]" wrote:

> Each individual installation is not a copy of the SAME project, it may be a
> replica of a prototype project involving similar work but each one is a
> different project. "Install Router" at 1st Street Location will require
> resource Bill to be there on Tuesday for 6 hours. "Install Router" at Main
> Street location will require resource Fred to be there for 4 hours on
> Wednesday. They're two totally different tasks, albeit with the same name
> and very similar actions being performed.
>
> You were talking about inserting "projects" into a master file. I usually
> think of that as being the master plan with a number of different project's
> on their plate. In your example, I'd call your "master project" the
> Project and it includes 45 summary tasks describing the installation of the
> equipment at each of 45 different locations. But I'd list every location as
> its own entitity. You don't link one location to another unless they really
> are contingent for some reason - perhaps you're setting up a network in a
> star topology and the location(s) chosen as the centre of the star need to
> have their equioment installed before the locations that connect to them so
> you can properly test the locations on the radials as you set them up. But
> other than that sort of thing, the 45 summary tasks describing each
> location's installation will initially be in parallel. Then you can set the
> Project start, assign your reources, and do resource leveling to generate
> the final schedule eazy peazy, just like you want to. And far simpler both
> to organize and track than doing master project / inserted subprojects. 45
> summary tasks with a dozen or so subtasks in each isn't an especially large
> project - I once read a Boeing 747 assembly plan was about 85000 tasks and
> Project itself allows up to about 1 million tasks. 500 or so total tasks is
> a piece of cake.
> --
> Steve House [MVP]
> MS Project Trainer & Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "Greg DePasse" <Greg DePasse@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> news:95766BA8-2480-4EB2-8BE4-4E4C5798FA07@xxxxxxxxxxxxxxxx
> > Actually what is proposed is not a usable solution for me. I am trying to
> > schedule a master project (install equipment at 45 locations). Each
> > location
> > has the same set of tasks (perform site survey, order equipment, install
> > site
> > 2 months after ordering equipment,...) and I don't really care when they
> > each
> > start. I want to set a master start date and then let MS Project do
> > resource
> > leveling and figure out when I can plan to get to all the sites. I also
> > want
> > to be able to change a duration or add a task in the "generic" schedule
> > and
> > have that change reflected in all the site schedules. Is there any way to
> > do
> > this other than to not bother with a subproject and instead copy and paste
> > my
> > core set of 6 tasks over and over (and hope I never need to make a change
> > to
> > those 6 tasks)?
> >
> > Thanks,
> > Greg
> >
> >
> > "Steve House [MVP]" wrote:
> >
> >> Make a copy of the file, change its start date, and insert the copy.
> >> That's
> >> not so farfetched as each iteration of the subproject really is a
> >> separate
> >> project in its own right with its own dstart, end, resources, budget,
> >> etc.
> >>
> >> Steve House [MVP]
> >>
> >> "GG" <GG@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> >> news:28CCD9DC-1DEB-4CBC-AC28-1BB350963D41@xxxxxxxxxxxxxxxx
> >> >I have a sub project that will be repeating for each phase and I would
> >> >like
> >> > to insert this sub project into my master/consolidated project. But,
> >> > Project
> >> > 2003 reports to me that I can only insert only once. The actual message
> >> > I
> >> > get
> >> > is:
> >> >
> >> > "A project can be inserted only once in a consolidated project"
> >>
> >>
> >>
>
>
.



Relevant Pages

  • Re: MSSQL2K and MSSQL side by side in clustered environment
    ... We have 3 disk resources in a cluster group dedicated to the SQL Server 2005 ... We did try the installation without having sql network name and ip address ... > You need to start out with a disk resource in its own resource group. ...
    (microsoft.public.sqlserver.clustering)
  • Re: A real package manager in action
    ... It's already more hard work for the user than a package manager would ... resource is missing it sets a flag in a system variable. ... Why not let the maintainer write the dependency file after all you ... All this can be done now and if you opt for manual installation ...
    (comp.sys.acorn.apps)
  • Re: Attention Word 2007 B2TR users [Problems with Gallery samples - Building Blocks.dotx]
    ... When you start one of the Office 2007 apps the first time the program checks the currently logged in users %appdata% folder location ... find a Building Blocks.dotx file in the %appdata% area, it copies the 'master' one over from the Program Files folder for Office ... For the Office 2007 Beta 2 Technical refresh, the installation updated the Master copy, but since there was still a 'user area' file ...
    (microsoft.public.office.misc)
  • Install doesnt assign drive letter to slave drive
    ... 2+ yr old 40G WD hard drive as the master and only hard ... does Windows Disk Management in the new XP installation, ... In Disk ... NTFS, 111.78 GB capacity, Healthy ). ...
    (microsoft.public.windowsxp.setup_deployment)
  • Re: Problem with Refference Ribon
    ... As an additional note, there are two Building Blocks.dotx files, a master ... copy in the Office installation path and a personal copy in your profile. ... corrupt and prompt for a reinstall. ... "Terry Farrell" wrote: ...
    (microsoft.public.word.application.errors)