Re: Uploading changes to Project Server
- From: "new2msp" <new2msp@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Wed, 27 Apr 2005 14:38:42 -0700
OK then I must have done something wrong when initially setting this up
because I've tried that and it won't upload my data. I get a huge error
code. Maybe I'll go look at the App Config book and see if I left something
out??
Thank You! :) I greatly appreciate the help!
new2msp
"Dale Howard [MVP]" wrote:
> new2msp --
>
> Create your project with tasks, Durations, dependencies, constraints, notes,
> etc. Add resources to the project using Tools - Build Team from Enterprise,
> and then assign resources to each task as needed. Save your project to the
> Project Server database. When you are ready to publish, click Collaborate -
> Publish - All Information to "push" all of the project information to PWA.
> If you make changes to the project, remember to save and publish the project
> using Collaborate - Publish - All Information. When you receive task
> updates from team members and process the updates into the project plan,
> always remember to finish the update operation by clicking Collaborate -
> Publish - All Information. Doing so will guarantee that your project
> information in Microsoft Project and the project information in PWA are
> synched up. Hope this helps.
>
> --
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> http://www.msprojectexperts.com
> "We wrote the book on Project Server"
>
>
> "new2msp" <new2msp@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> news:B0477F84-B68A-4B30-8F0A-EEED61B2CFB3@xxxxxxxxxxxxxxxx
> > Hello!! What needs to be done to allow me to make my changes in Project
> > Pro
> > and then Publish my changes in Project Server? What changes can be
> > uploaded
> > and what changes cannot?
> >
> > THANKS! :)
>
>
>
.
- Follow-Ups:
- Re: Uploading changes to Project Server
- From: Dale Howard [MVP]
- Re: Uploading changes to Project Server
- References:
- Uploading changes to Project Server
- From: new2msp
- Re: Uploading changes to Project Server
- From: Dale Howard [MVP]
- Uploading changes to Project Server
- Prev by Date: RE: Project scheduling quirk
- Next by Date: Re: PRINCE2
- Previous by thread: Re: Uploading changes to Project Server
- Next by thread: Re: Uploading changes to Project Server
- Index(es):
Relevant Pages
|