Re: Uploading changes to Project Server



new2msp --

Create your project with tasks, Durations, dependencies, constraints, notes,
etc. Add resources to the project using Tools - Build Team from Enterprise,
and then assign resources to each task as needed. Save your project to the
Project Server database. When you are ready to publish, click Collaborate -
Publish - All Information to "push" all of the project information to PWA.
If you make changes to the project, remember to save and publish the project
using Collaborate - Publish - All Information. When you receive task
updates from team members and process the updates into the project plan,
always remember to finish the update operation by clicking Collaborate -
Publish - All Information. Doing so will guarantee that your project
information in Microsoft Project and the project information in PWA are
synched up. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


"new2msp" <new2msp@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:B0477F84-B68A-4B30-8F0A-EEED61B2CFB3@xxxxxxxxxxxxxxxx
> Hello!! What needs to be done to allow me to make my changes in Project
> Pro
> and then Publish my changes in Project Server? What changes can be
> uploaded
> and what changes cannot?
>
> THANKS! :)


.



Relevant Pages

  • Re: THOUSANDS of extra Resources added
    ... Enterprise Project Trainer/Consultant ... "We wrote the book on Project Server" ... >>> resources were replaced with enterprise resources. ... >>>> When you say "created offline with generic local resources and then ...
    (microsoft.public.project.pro_and_server)
  • Re: published project not listed in open from Microsoft project server dialog box
    ... If you are moving to Project Server, then you will need to import your ... click Tools - Enterprise Options - ... Make sure that you match up the resources ... > a enterprise project in a way that it can use non-entrprise resources. ...
    (microsoft.public.project.pro_and_server)
  • Re: synch PWA users/resources with existing resources on an MPP?
    ... Ryan -- ... logged into Project Server through Microsoft Project Professional. ... Click Tools - Enterprise Options - Import Project to Enterprise ... On the page that deals with resources, match each resource in the .mpp ...
    (microsoft.public.project.pro_and_server)
  • Re: THOUSANDS of extra Resources added
    ... Listen to Dale and use the Import ... Did you use Tools - Enterprise ... Why don't they log into Project Server, create a new project, ... >>> resources were replaced with enterprise resources. ...
    (microsoft.public.project.pro_and_server)
  • Actual Work/ Timesheets
    ... While using the Timesheets on the Project Server to update ... or more resources assigned to a task. ... updates the actuals & send PM fo approvals. ...
    (microsoft.public.project.pro_and_server)