Re: not started yet + graphical indicators

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance



Hi Jan,

I use (% complete) as a formula
and
Is greater than equal to 80: green
Is within 25,80: orange
Is less than or equal to 25: red

Unfortunately this formula counts tasks not started as 'red' too.

Any suggestions?




D.

"Jan De Messemaeker" wrote:

> What criteria do you use for the indicators?
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> http://users.online.be/prom-ade/
> +32-495-300 620
> "D." <D.@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
> news:954BC800-8E3F-47AF-8094-3AD56655EB66@xxxxxxxxxxxxxxxx
> > Hi guys,
> >
> > I set up a % complete graphical indicator that works rather well. However
> > even when a task has not started yet, it still triggers a 'red' indicator.
> I
> > 'd like to find a way to avoid that and have a red signal ONLY when a task
> is
> > started and delayed. Any ideas?
> >
> > Thanks,
> >
> >
> > D.
>
>
>
.



Relevant Pages

  • Re: not started yet + graphical indicators
    ... indicator, including tasks with past due dates... ... "Jan De Messemaeker" wrote: ... > Equals 0: no indicator ... >>> Microsoft Project Most Valuable Professional ...
    (microsoft.public.project)
  • Re: not started yet + graphical indicators
    ... Equals 0: no indicator ... >> Jan De Messemaeker ... >> Microsoft Project Most Valuable Professional ...
    (microsoft.public.project)
  • Re: not started yet + graphical indicators
    ... >> indicator, including tasks with past due dates... ... >>> HTH ... >>> Jan De Messemaeker ... >>> Microsoft Project Most Valuable Professional ...
    (microsoft.public.project)
  • Re: not started yet + graphical indicators
    ... > indicator, including tasks with past due dates... ... >> HTH ... >> Jan De Messemaeker ... >> Microsoft Project Most Valuable Professional ...
    (microsoft.public.project)
  • Re: s///x
    ... > Redundant constructs are an important indicator *against* the authors ... > competence. ... That's why it is generally a good idea to avoid them. ...
    (comp.lang.perl.misc)