Re: Compare Utility with External Tasks
- From: John <mjensen@xxxxxxxxxxxx>
- Date: Fri, 15 Apr 2005 09:14:38 -0700
In article <9E9BB4C5-20DC-4A3A-A060-D5C4C07ADB87@xxxxxxxxxxxxx>,
"ET902" <ET902@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:
> Beast is the word for it. I did not create the schedule, I just perform
> schedule analysis on it. The master schedule is made up of 41 seperate
> schedules...yep, 41 schedules for 7000 tasks!! This one subproject is the
> only one I am having a problem with. It almost has to be some sort of
> corruption.
> I would send you the schedule to look at ( just out of a sense of defeat)
> but it is loaded with proprietary info so I can't.
> Do you know of anyway that I can make the linked tasks not be linked
> tasks. In other words, like in excel when you do a paste special values, so
> that the information and links would "look like" they are not external.
> Thanks for your help on this by the way.
ET,
I assume the one subproject you are having problems with is the 160 task
file with 36 external links that you mentioned in your original post.
The quantity of subprojects and total size of the master shouldn't be
any problem. I personally worked with 70+ subprojects in a master of
approx. 10K tasks. The only issue with maintaining that complex
structure is that it requires expertise, experience, and a lot of
patience and discipline.
You mention you suspect corruption. Is one or more of the subprojects
that do NOT seem to cause a problem about the same number of tasks as
the file you suspect has a problem? If so, take a look at the file size
of the subproject(s) without an issue and the file with an issue. If the
file with an issue is significantly larger, (e.g. other files are 100K
while the suspect file is 5 Meg), then yes, the file is corrupt. For
tips and tricks for dealing with corrupt files go to the MVP website at:
http://www.mvps.org/project/faqs.htm
and look at FAQ 43 - File Bloat? Might be corruption
With regard to your files having proprietary information, as I mentioned
previously I have a macro that will de-sensitize the file. If
interested, contact me direct. A similar macro is also available on
fellow MVP, Jack Dahlgren's website at:
http://masamiki.com/project/macros.htm
Look for the "scrub" macro. Either my macro or Jack's macro will remove
all sensitive information yet will not affect file structure.
And finally, yes, there is a method for converting externally linked
tasks to internally linked tasks. I have a macro that will do that but
it is NOT freeware. If you want more information, contact me direct.
Hope this helps.
John
Project MVP
.
- References:
- Compare Utility with External Tasks
- From: ET902
- Re: Compare Utility with External Tasks
- From: John
- Re: Compare Utility with External Tasks
- From: ET902
- Re: Compare Utility with External Tasks
- From: John
- Re: Compare Utility with External Tasks
- From: ET902
- Re: Compare Utility with External Tasks
- From: John
- Re: Compare Utility with External Tasks
- From: ET902
- Compare Utility with External Tasks
- Prev by Date: RE: Progress on Tasks prior to the start of the project.
- Next by Date: Filter
- Previous by thread: Re: Compare Utility with External Tasks
- Next by thread: suretrak
- Index(es):
Relevant Pages
|