Re: Report of estimated % complete.



Hello Dave,
Why not use the Earned Value data : what you want is almost the BCWS,
compared with the BCWP and the ACWP.
Have a look in the Help for these fields.

Gérard Ducouret

"DaveFusion" <DaveFusion@xxxxxxxxxxxxxxxxxxxxxxxxx> a écrit dans le message
de news:B0AC7730-5DEA-4437-B184-A2C6315CBFD8@xxxxxxxxxxxxxxxx
> Guys & Gals,
> I have a request to produce a report which shows 'what the % complete
should
> be if all tasks are running on schedule'.
>
> The only way I could think of doing this would be manually 'update to
> schedule' all tasks, then Copy/Cut the % complete column, close the plan
> without saving ( or possibly use the undo function ), paste the vales into
a
> user defined column and then print out.
>
> I'm sure somebody out there has some natty little tool or macro that could
> do all this for me at the touch of a mouse - if you're that person please
let
> me know !!!
>
> Thanks


.



Relevant Pages

  • Re: Earned Value Field Categories
    ... I'm not sure you would ever roll up the assignment to the specific resource, ... between ACWP BCWP and BCWS. ...
    (microsoft.public.project)
  • Re: Bcwp/bcws
    ... If SPI exceeds 1.0 (you are ahead of schedule) then BCWP will exceed BCWS. ...
    (microsoft.public.project)
  • Interpreting BCWP Caculation: Part II
    ... ACWP £20.00 ... BCWP £80.00 ... BCWS £80.00 ... How do I interpret the EVA information in Task Usage View? ...
    (microsoft.public.project)
  • Re: Earned Value Field Categories
    ... If the project is performed exactly as planned then there is no difference between ACWP BCWP and BCWS. ... Resource fields do not make much sense in determining Earned value. ...
    (microsoft.public.project)
  • Re: Earned Value Field Categories
    ... look at Fields Reference via Help it gives me six Field Categories for BCWS, ... six for BCWP and six for ACWP. ... to different views (Gantt, Resource, Task etc.), I’m actually at a loss to ...
    (microsoft.public.project)