Re: Task Constraints

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



This is exactly the situation you interpret, Steve. The work around is pretty
complex and will take a bit to figure out. I think it's an opportunity for MS
to make an improvement by changing the forced date selection to an hours
option. I am working in Project 02, so maybe it's already changed in newer
versions.

"Steve House [Project MVP]" wrote:

> I assume the idea here is to insure the task will finish the same day it
> starts regardless of what day that happens to be. There's no way to use a
> constraint to do that - you can say "Start No Later Than 15 Apr at 9am" but
> you can't "Always Start Before 9am" by using constraints. The work around
> is to create a calendar that show hours of work from, say, 07:59 to 08:59.
> Insert a task with 1 minute duration and put it in the middle of the link
> between the task you need to start before 9 and its predecessor. Set your 1
> hour calendar to be that task's task calendar. Now regardless of when the
> predecessor ends, the pseudo task can only happen between 7:59 and 8:59am
> and the one you're trying to control will follow immediately after.
> --
> Steve House [MVP]
> MS Project Trainer & Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "Lowkey" <Lowkey@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> news:41A608BA-369A-4C37-8C1E-EA7A2735E372@xxxxxxxxxxxxxxxx
> > Thanks. Is there any way to set the tasks constraints in hours, instead of
> > the using the default calendar? I have a task that must start no later
> > than 9
> > am because it must be finished in the same day.
> >
> > "Steve House [Project MVP]" wrote:
> >
> >> Go to the task information form, advanced tab and change the constraint
> >> to
> >> As Soon As Possible.
> >>
> >> --
> >> Steve House [MVP]
> >> MS Project Trainer & Consultant
> >> Visit http://www.mvps.org/project/faqs.htm for the FAQs
> >>
> >> "Lowkey" <Lowkey@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> >> news:B069C8D8-B427-41A0-9512-B81FCFAA3428@xxxxxxxxxxxxxxxx
> >> > How do I remove constraints from a Task in Project 02 without deleting
> >> > the
> >> > task and creating a new one.
> >> >
> >>
> >>
>
>
.



Relevant Pages

  • Re: Task Constraints
    ... The idea is that a successor will usually be able to start as soon as its predecessor allows it to. ... Imagine Task A as predecessor to 8-hour task B, and we use the conventional work calendar. ... MS Project Trainer & Consultant ... you can't "Always Start Before 9am" by using constraints. ...
    (microsoft.public.project)
  • Re: The C Boolean Fallacy Crack
    ... in response to a calendar. ... Better welcome constraints now or ... Dianna will hopefully dislike them except for you. ...
    (sci.crypt)
  • Re: How to Find Overlapping Date Ranges in a Table
    ... ranges and some overlapping ranges, ... And you then need to add constraints to prevent this from happening ... You should have a Calendar table in your schema. ... FROM FoobarPeriods AS F, Calendar AS C ...
    (microsoft.public.sqlserver.programming)
  • Re: Calendar duration
    ... Txs Rob and Steve. ... When you enter a duration such as "3 days" Project must convert your entry to minutes - the Hours per Day, Hours per Week, and Days per Month fields on that page set the conversion factors it uses. ... You set your working day times in the calendar on Tools/ChangeWorkingTime in the menu. ... How do I fix these problems? ...
    (microsoft.public.project)
  • Re: Task Delaying start
    ... Your thoughts are right on but I refrain from constraints so there are none ... no lag and no resource contention. ... You should also check the working time calendar to make sure the 3 day ...
    (microsoft.public.project)