RE: Dependencies



I set the task constraints to start as soon as possible, but the dates will
not change based on the inserted dependencies.

"toby0" wrote:

> Check your constraints one of the tasks may be set "start no earlier/later".
> Ensure the following task is set ASAP. This is probably the problem.
>
> "Harry" wrote:
>
> > I am working on MSP 2002, and cannot get the dependency to work for two task.
> > I have linked one task to another but the dates will not change. I checked
> > for rollup task linkage.
> >
> > What should I be doing?
.