RE: Dependencies
- From: "Harry" <Harry@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Thu, 7 Apr 2005 06:19:02 -0700
I set the task constraints to start as soon as possible, but the dates will
not change based on the inserted dependencies.
"toby0" wrote:
> Check your constraints one of the tasks may be set "start no earlier/later".
> Ensure the following task is set ASAP. This is probably the problem.
>
> "Harry" wrote:
>
> > I am working on MSP 2002, and cannot get the dependency to work for two task.
> > I have linked one task to another but the dates will not change. I checked
> > for rollup task linkage.
> >
> > What should I be doing?
.
- Follow-Ups:
- Re: Dependencies
- From: Jan De Messemaeker
- Re: Dependencies
- References:
- Dependencies
- From: Harry
- RE: Dependencies
- From: toby0
- Dependencies
- Prev by Date: Re: Duration and dates
- Next by Date: RE: Progress display on "Group by" Summary tasks
- Previous by thread: RE: Dependencies
- Next by thread: Re: Dependencies
- Index(es):