Re: Dependencies
- From: "Jan De Messemaeker" <jandemes at prom hyphen ade dot be>
- Date: Thu, 7 Apr 2005 15:47:03 +0200
Hi,
Is in tools, Options, Calculation, Calculation set to automatic?
If yes, have you ever had a message about circular relationships?
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Harry" <Harry@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:A183F929-282C-4E84-A566-40282A835BE0@xxxxxxxxxxxxxxxx
> I set the task constraints to start as soon as possible, but the dates
will
> not change based on the inserted dependencies.
>
> "toby0" wrote:
>
> > Check your constraints one of the tasks may be set "start no
earlier/later".
> > Ensure the following task is set ASAP. This is probably the problem.
> >
> > "Harry" wrote:
> >
> > > I am working on MSP 2002, and cannot get the dependency to work for
two task.
> > > I have linked one task to another but the dates will not change. I
checked
> > > for rollup task linkage.
> > >
> > > What should I be doing?
.
- References:
- Dependencies
- From: Harry
- RE: Dependencies
- From: toby0
- RE: Dependencies
- From: Harry
- Dependencies
- Prev by Date: more custom field "start" and "finish"
- Next by Date: MS Project
- Previous by thread: RE: Dependencies
- Next by thread: Re: Dependencies
- Index(es):
Relevant Pages
|
Loading