Re: Dependencies



Hi,

Is in tools, Options, Calculation, Calculation set to automatic?

If yes, have you ever had a message about circular relationships?
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Harry" <Harry@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:A183F929-282C-4E84-A566-40282A835BE0@xxxxxxxxxxxxxxxx
> I set the task constraints to start as soon as possible, but the dates
will
> not change based on the inserted dependencies.
>
> "toby0" wrote:
>
> > Check your constraints one of the tasks may be set "start no
earlier/later".
> > Ensure the following task is set ASAP. This is probably the problem.
> >
> > "Harry" wrote:
> >
> > > I am working on MSP 2002, and cannot get the dependency to work for
two task.
> > > I have linked one task to another but the dates will not change. I
checked
> > > for rollup task linkage.
> > >
> > > What should I be doing?


.



Relevant Pages


Loading