RE: Dependencies



Check your constraints one of the tasks may be set "start no earlier/later".
Ensure the following task is set ASAP. This is probably the problem.

"Harry" wrote:

> I am working on MSP 2002, and cannot get the dependency to work for two task.
> I have linked one task to another but the dates will not change. I checked
> for rollup task linkage.
>
> What should I be doing?
.