Re: Late Dates incorrect after indenting under Summary Task
From: JackD (momokuri_at_gmail)
Date: 02/23/05
- Next message: Joe: "RE: custom filter"
- Previous message: Paul Schaefer: "Re: Task Reporting by Resource - All Projects"
- In reply to: Sean: "Re: Late Dates incorrect after indenting under Summary Task"
- Next in thread: Steve House [MVP]: "Re: Late Dates incorrect after indenting under Summary Task"
- Messages sorted by: [ date ] [ thread ]
Date: Wed, 23 Feb 2005 10:33:44 -0800
Um.... It works fine for me. There is no change. I can't reproduce your
problem.
Which version of project are you using?
Are all tasks set to be start as soon as possible?
-- -Jack ... For project information and macro examples visit http://masamiki.com/project . "Sean" <Sean@discussions.microsoft.com> wrote in message news:2112CCC3-04E6-4438-8ABE-81E853992169@microsoft.com... > Let me explain better. > > Create a project with the following info. The summary task is not Linked. > Don't indent it under the summary until you've added all the tasks. All > relationships are FS. Use a 5 day duration for all tasks. Insert the late > start field into your table. > > Now, indent all the tasks under the sumary task. Watch the late dates > change. They shouldn't becuase there is no link or relationship to the > summary line. Microsoft has acknowledged the problem but has made no promise > to fix it. I've heard of some work around's but not found one that is 100% > > Thanks > Sean > > ID NAME PRED > 1 summary > 2 Start Milestone #1 > 3 Activity #1 2 > 4 Activity #2 3 > 5 Activity #3 4 > 6 Finish Milestone #1 5,10 > 7 Start Milestone #2 > 8 Activity #4 7 > 9 Activity #5 8 > 10 Activity #6 9 > 11 Start Milestone # 3 > 12 Activity #7 11 > 13 Activity #8 12 > 14 Activity #9 13 > 15 Finish Milestone #2 14 > > > > > "Steve House [MVP]" wrote: > > > I'm not aware of any "bug" like you're describing. The total slack time of > > a task is the amount of time it could be delayed without delaying the > > project finish, in a nutshell. Imagine Summary Task A with subtasks A1 > > (3d), A2 (4d), & A3 (5d). The subtasks are not linked so they occur in > > parallel, all starting the same day. Summary task A links to Summary X FS > > and Summary X in turn links FS to the Finish milestone. What are the late > > dates of A1, A2, & A3? Summary A's finish is determined by A3 so the late > > date of A3 and Summary A are the same. Only if Summary A is delayed past > > that point will Summary X be delayed, hence that is also the latest date it > > can finish without delaying the project's finish. The late finishes of A1 > > and A2 are also that same date as A3 (which is also the late finish of > > Summary A), since they could slip by 2 or 1 day respectively before they > > delay the finish of Summary A. I think that is what you're describing in > > your posting but where's the bug in that? That is exactly the way late > > starts and late finishes are supposed to be calculated and that's the way > > project does calculate them. And this is even with linking between the > > summary tasks, which is often considered a bad idea. The alternative > > linking would have A1, A2, and A3 all as predecessors to X1 and no links > > directly in or out of the summary tasks themselves but the results are > > exactly the same. > > > > If I'm missing something here, please give us some concrete example that > > demonstrates what you consider to be this bug - what Project gives you and > > what you think it should be giving you instead (and why you feel Project is > > wrong and your way is right). I'm really curious. > > -- > > Steve House [MVP] > > MS Project Trainer & Consultant > > Visit http://www.mvps.org/project/faqs.htm for the FAQs > > > > > > > > > > > > "Sean" <Sean@discussions.microsoft.com> wrote in message > > news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com... > > > Many of you know there is a "bug" in MS Project that affects the late > > > dates > > > and backward pass. > > > > > > If you indent a group of tasks under the summary task the late dates for > > > that group are changed by the summary task. A weird problem that only > > > surfaces when calculating total slack and the backward pass. > > > > > > I've heard of some people using MSO/MFO anchors at the end of thier > > > network > > > to solve this. Does anybody else have a solution. My company (a rather > > > large one) has submitted this to Microsoft and they acknowledge that it is > > > a > > > bug, but aren't planning on fixing it anytime soon. > > > > > > Please advise. > > > > > > Sean > > > > > > >
- Next message: Joe: "RE: custom filter"
- Previous message: Paul Schaefer: "Re: Task Reporting by Resource - All Projects"
- In reply to: Sean: "Re: Late Dates incorrect after indenting under Summary Task"
- Next in thread: Steve House [MVP]: "Re: Late Dates incorrect after indenting under Summary Task"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|