Re: Late Dates incorrect after indenting under Summary Task

From: JackD (momokuri_at_gmail)
Date: 02/23/05


Date: Wed, 23 Feb 2005 10:33:44 -0800

Um.... It works fine for me. There is no change. I can't reproduce your
problem.
Which version of project are you using?
Are all tasks set to be start as soon as possible?

-- 
-Jack  ... For project information and macro examples visit
http://masamiki.com/project
.
"Sean" <Sean@discussions.microsoft.com> wrote in message
news:2112CCC3-04E6-4438-8ABE-81E853992169@microsoft.com...
> Let me explain better.
>
> Create a project with the following info.  The summary task is not Linked.
> Don't indent it under the summary until you've added all the tasks.  All
> relationships are FS. Use a 5 day duration for all tasks.  Insert the late
> start field into your table.
>
> Now, indent all the tasks under the sumary task.  Watch the late dates
> change.  They shouldn't becuase there is no link or relationship to the
> summary line.  Microsoft has acknowledged the problem but has made no
promise
> to fix it.  I've heard of some work around's but not found one that is
100%
>
> Thanks
> Sean
>
> ID             NAME                              PRED
> 1 summary
> 2 Start Milestone #1
> 3 Activity #1                          2
> 4 Activity #2                          3
> 5 Activity #3                          4
> 6 Finish Milestone #1         5,10
> 7 Start Milestone #2
> 8 Activity #4                           7
> 9 Activity #5                           8
> 10 Activity #6                           9
> 11 Start Milestone #                 3
> 12 Activity #7                           11
> 13 Activity #8                           12
> 14 Activity #9                           13
> 15 Finish Milestone #2            14
>
>
>
>
> "Steve House [MVP]" wrote:
>
> > I'm not aware of any "bug" like you're describing.  The total slack time
of
> > a task is the amount of time it could be delayed without delaying the
> > project finish, in a nutshell.  Imagine Summary Task A with subtasks A1
> > (3d), A2 (4d), & A3 (5d).  The subtasks are not linked so they occur in
> > parallel, all starting the same day.  Summary task A links to Summary X
FS
> > and Summary X in turn links FS to the Finish milestone.  What are the
late
> > dates of A1, A2, & A3?  Summary A's finish is determined by A3 so the
late
> > date of A3 and Summary A are the same.  Only if Summary A is delayed
past
> > that point will Summary X be delayed, hence that is also the latest date
it
> > can finish without delaying the project's finish.  The late finishes of
A1
> > and A2 are also that same date as A3 (which is also the late finish of
> > Summary A), since they could slip by 2 or 1 day respectively before they
> > delay the finish of Summary A.  I think that is what you're describing
in
> > your posting but where's the bug in that?  That is exactly the way late
> > starts and late finishes are supposed to be calculated and that's the
way
> > project does calculate them.  And this is even with linking between the
> > summary tasks, which is often considered a bad idea.  The alternative
> > linking would have A1, A2, and A3 all as predecessors to X1 and no links
> > directly in or out of the summary tasks themselves but the results are
> > exactly the same.
> >
> > If I'm missing something here, please give us some concrete example that
> > demonstrates what you consider to be this bug - what Project gives you
and
> > what you think it should be giving you instead (and why you feel Project
is
> > wrong and your way is right).  I'm really curious.
> > -- 
> > Steve House [MVP]
> > MS Project Trainer & Consultant
> > Visit http://www.mvps.org/project/faqs.htm for the FAQs
> >
> >
> >
> >
> >
> > "Sean" <Sean@discussions.microsoft.com> wrote in message
> > news:8D16920B-D1B6-47F2-B279-B190C3F654F4@microsoft.com...
> > > Many of you know there is a "bug" in MS Project that affects the late
> > > dates
> > > and backward pass.
> > >
> > > If you indent a group of tasks under the summary task the late dates
for
> > > that group are changed by the summary task.  A weird problem that only
> > > surfaces when calculating total slack and the backward pass.
> > >
> > > I've heard of some people using MSO/MFO anchors at the end of thier
> > > network
> > > to solve this.  Does anybody else have a solution.  My company (a
rather
> > > large one) has submitted this to Microsoft and they acknowledge that
it is
> > > a
> > > bug, but aren't planning on fixing it anytime soon.
> > >
> > > Please advise.
> > >
> > > Sean
> > >
> >
> >


Relevant Pages

  • Re: Late Dates incorrect after indenting under Summary Task
    ... about task 11's predecessor, but then I tried it both ways - no predecessor ... > Don't indent it under the summary until you've added all the tasks. ... > 2 Start Milestone #1 ... >> I'm not aware of any "bug" like you're describing. ...
    (microsoft.public.project)
  • Re: Late Dates incorrect after indenting under Summary Task
    ... or do you mean its name is Start Milestone #3? ... "Sean" wrote in message ... >> I'm not aware of any "bug" like you're describing. ... Imagine Summary Task A with subtasks A1 ...
    (microsoft.public.project)
  • Re: JTextPane: Workaround for invisible text with hanging indents?
    ... > See below, with NegativeFirstLineIndentParagraphView2. ... It looks like this Bug ID comment from 2001 is fully applicable today: ... had working TABs, but had problems with a negative first line indent. ...
    (comp.lang.java.gui)
  • Re: Combo Box Display issues
    ... Sean, is this Access 2003? ... your machine may have downloaded Service Pack 3 for Office 2003. ... There's a bug in the SP where the combo whose RowSource is a table that has something in its Format property. ... but I dont know how to start troubleshooting. ...
    (microsoft.public.access.formscoding)
  • Re: Heads up --- Thinking about UDP and tunneling
    ... indent seems to be making ... Bug in indent, same as in s9indent. ... but the original code has fancy formatting ...
    (freebsd-net)