Re: Resource Availability Setting vs. Leveling

From: Jan De Messemaeker (jandemes)
Date: 02/17/05


Date: Thu, 17 Feb 2005 17:26:29 +0100

Hi Michael,

You gave the answer yourself: give them a calendar that covers 50% of the
time (e.g. morning only)
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
"michael" <michael@discussions.microsoft.com> schreef in bericht
news:F04CA79A-B361-4FAC-87FF-69932105BFA8@microsoft.com...
> I'm having a bit of trouble using the Resource Availability setting for
> personnel in a project.  I have people who will be available 100% then 50%
of
> the time.  I set the parameters for each person then leveled my project.
Any
> tasks that were set to resource usage of 100% were not scheduled while the
> person was at 50% on the schedule.  If I make the person available only
50%
> of the time using their calendar it levels just fine.
>
> It does appear that if I change the resource usage on the task from 100%
to
> 50% it will level properly.  however, that sort of defeats the purpose
since
> I would like Project to figure what tasks can be done during the time the
> people will be 50%.
>
> Is there a way to set their availability to 50% and have the tasks
schedule
> properly without having to change the settings on the task?


Relevant Pages

  • Resource Availability Setting vs. Leveling
    ... I'm having a bit of trouble using the Resource Availability setting for ... tasks that were set to resource usage of 100% were not scheduled while the ... It does appear that if I change the resource usage on the task from 100% to ... Is there a way to set their availability to 50% and have the tasks schedule ...
    (microsoft.public.project)
  • Re: i was clutching to attribute you some of my allied worths
    ... please pronouncing sediment for instance my calendar. ... Whoever divert once, widen so, then schedule around the abortion ... Fucking don't buy reportedly while you're scaning below a delightful ... Many behalfs very sigh the puzzled campaign. ...
    (sci.crypt)
  • RE: What am I doing wrong tracking progress?
    ... to record it in the schedule. ... calendar Either create a new calendar ... Project and tell it, "My resource worked on this task for six hours, ... The correct amount of work for the task is ...
    (microsoft.public.project)
  • Re: Outlook and dates
    ... If a task positively can only take place on the first of the month, create a calendar that shows the first of each month as the only working day and assign that calendar as the task calendar for the task of interest. ... Then the only days it will be scheduled on will be the first of the month - if its predecessor finishes the 15th of August, that task will be scheduled the 1st of September. ... If the contract requires you to ship on the 1st of September, it's up to you to arrange the predecessors and schdule their resources so its possible to ship on schedule - merely fixing the ship date to September 1 won't make it happen. ...
    (microsoft.public.project)
  • Re: Exporting Calendar View & linking Excel Data to project Table
    ... You manage your prduct development on a schedule ... > external community using a Calendar [Attending a Conference for a key staff ... So my thought is to have the top of the MSP file manage the ... and tracking major defined projects. ...
    (microsoft.public.project)