Re: Calculate effort for a short duration task between dates

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance

brotherescott_at_yahoo.com
Date: 02/08/05


Date: 8 Feb 2005 06:06:02 -0800

I was thinking of using the deadline approach as you suggested but
everyone was telling me not to use had constraints because they can
cause problems later on. I think that this is a case where it is
needed.
I had tried another approach. I put in a build schedule block of time
and then put in a build task after it. I then put in a negative lag
time to push it up into the build block of time and then had the next
task in the list us both of these lines as predecessors. This allowed
me to not put a resource to the the build block of time but I could put
a resource onto the actual build time.
 It kind of works but I think I am going to try the deadline approoach
to see how it all works out.

Thanks
Scott



Relevant Pages

  • Re: How to show the resource estimated hrs
    ... Place that as a date in the deadline filed for the task. ... task by the resource modified by the units of the resource applied ... working 50% of the time on that task will take just over 1 week of duration. ... Think of it this way, if the effort needed to complete the task is 40 hrs, ...
    (microsoft.public.project)
  • Re: Calculate effort for a short duration task between dates
    ... A deadline is not the same thing as a constraint and I would agree very ... it goes later but it doesn't actually force the schedule into any particular ... Constraints, OTOH, actually do force the schedule to behave in ... This allowed> me to not put a resource to the the build block of time but I could put> a resource onto the actual build time. ...
    (microsoft.public.project)
  • Re: How to show the resource estimated hrs
    ... of how project works and calculates work, duration and units of resources. ... will find that the units of resource applied daily to the task is 13%. ... when you tell us the deadline parameters, you gave it in weeks not in hours. ... There are 40 hrs is a week. ...
    (microsoft.public.project)
  • Re: "Start no earlier than" always the same as "Start date"
    ... In your original post you say that you enter a start no earlier than constraint and then seem surprised that's where Project places the task. ... MSP does not allocate resource A, or any other resource, to tasks. ... Now I look at the schedule and see if the computed dates meet the business objectives of the project - finishing on deadline or coming in late. ... Project does not replace your knowledge of the resources and their qualifications or your expertise on how the project needs to be organized. ...
    (microsoft.public.project)
  • Re: applying resource availability constraints to a finish date sc
    ... can get done by the required deadline. ... I need to be able to schedule "as late as possible". ... Remove all constraints. ... When I set thier availability dates in the Resource Information screen, ...
    (microsoft.public.project)