Re: start & finish dates - what happens to dates inbetween
From: AngePaton (AngePaton_at_discussions.microsoft.com)
Date: 01/06/05
- Next message: GOALIE20: "Re: How do I show the % complete (planned) that will change my sta"
- Previous message: JulieD: "Re: pushing back a whole project"
- In reply to: Steve House [MVP]: "Re: start & finish dates - what happens to dates inbetween"
- Next in thread: Steve House [MVP]: "Re: start & finish dates - what happens to dates inbetween"
- Reply: Steve House [MVP]: "Re: start & finish dates - what happens to dates inbetween"
- Reply: JulieS: "Re: start & finish dates - what happens to dates inbetween"
- Messages sorted by: [ date ] [ thread ]
Date: Thu, 6 Jan 2005 07:41:08 -0800
Thanks Steve, that has worked well, however, there is one little problem that
you might be able to help with, as some of my data in the columns is large,
the columns display ### instead of the numbers.
I have not been able to widen the columns, no matter what changes to setup
are made, also am I right in thinking that the reports can't be exported as
my boss really wants a bar chart so I need to export to excel.
Many thanks
"Steve House [MVP]" wrote:
> Have you looked in the Reports menu and examined the Custom Reports option?
> In custom you'll find a listing for a Crosstab report, which is just another
> name for what Excel calls a pivot table report. If you select Crosstab and
> choose Edit, you can choose either tasks or resources for the rows and you
> can edit the field to summarize to be Work, among other things. When I run
> it, I get a report that shows weeks as columns, resources as rows with their
> tasks indented under them (an option you can turn on or off as you wish) and
> the table shows the total work done by that resource week by week. If a
> task runs more than 1 week, the work to be done in each week is apportioned
> out into the week where it takes place, NOT accumulated into the week during
> which the task begins as you said you've been getting. That sure sounds like
> the report you're trying to generate and you don't even need to mess around
> exporting to Excel at all - it's right there in Project's standard report
> packge right out of the box. True, it is a static snapshot, but then a
> Pivot Table report in Excel is also a static object and an exception to the
> automatic recalculation behaviour usually associated with Excel worksheets
> and formulae.
>
> --
> Steve House [MVP]
> MS Project Trainer & Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "AngePaton" <AngePaton@discussions.microsoft.com> wrote in message
> news:C6B235C1-DD1B-433D-820F-AD9C094D89F1@microsoft.com...
> >I have a large project that I need to create a pivot table and various
> > reports on. Th e pivot table needs to display by week, the amount of hours
> > that are required by each resource. However, I can only export Start &
> > Finsih
> > dates to Excel, I am unable to work out how to create a pivot table that
> > will
> > show that a resource is working on a task over 3 months so Wk1 = 16 hrs
> > effort, wk2 etc..... Using grouping on the pivot doesn't work as it only
> > shows the week the task starts in.
> > Does Project have a 'work effort by week' report? The 'resource usage'
> > report gives me what I want, but I can't export it to Excel, is there a
> > way????
>
>
- Next message: GOALIE20: "Re: How do I show the % complete (planned) that will change my sta"
- Previous message: JulieD: "Re: pushing back a whole project"
- In reply to: Steve House [MVP]: "Re: start & finish dates - what happens to dates inbetween"
- Next in thread: Steve House [MVP]: "Re: start & finish dates - what happens to dates inbetween"
- Reply: Steve House [MVP]: "Re: start & finish dates - what happens to dates inbetween"
- Reply: JulieS: "Re: start & finish dates - what happens to dates inbetween"