Re: Managing Closed Projects???

Tech-Archive recommends: Speed Up your PC by fixing your registry

From: Dale Howard [MVP] ("Dale)
Date: 12/13/04


Date: Mon, 13 Dec 2004 09:42:12 -0700

Andrea --

If you want to leave the closed projects in the Project Server database and
still see the hours in the Portfolio Analyzer views, you can remove the
tasks for all closed projects from the timesheets of those projects' team
members by doing the following:

1. Open a closed project
2. Click Tools - Build Team from Enterprise
3. Set the Booking Type for each team member to Proposed
4. Click the OK button
5. Click Collaborate - Publish - All Information
6. Repeat steps 1-5 for every closed project

Hope this helps.

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"
"Andrea" <Andrea@discussions.microsoft.com> wrote in message 
news:EAD47548-1CAD-463D-80AF-16776052E095@microsoft.com...
> Hi,
>
> since we have implemented MsProject Server in January 2004, we have a long
> list of projects on the server.  Some of them are still open but some of 
> them
> are completed and must be closed.  I don't think that Microsoft thought of 
> a
> way to close completed projects so that users won't see tasks coming from
> projects that are closedin their time ***.
>
> In fact, we have a lot of complaints coming from users who have over a
> thousand tasks in their time *** and 50% of these tasks are coming from
> completed projects.
>
> Is there a way to manage completed project so that we can still see them 
> in
> the OLAP cube but not in time***.
>
> Thanks for your help.
> Andrea 