Re: Overallocation in resource with no tasks!

From: Rod Gill (rodsngtrap_at_hotmail.com)
Date: 11/18/04


Date: Fri, 19 Nov 2004 08:32:57 +1300

Hi,

Try saving the file to a .mpd database then opening from the .mpd file and
saving to .mpp again. That will clear most things.

-- 
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA 
development services
visit www.project-systems.co.nz/
Email rodg AT project-systems DOT co DOT nz
"Dave Nicholls" <david.nicholls@danaNOSPAM.com> wrote in message 
news:eSKjwQYzEHA.3708@TK2MSFTNGP14.phx.gbl...
> Hi.
>
> I've been trying to update a plan where one of my resources is leaving the
> company.  I've changed their resource availability so that it ends on 
> their
> leaving date.  After this I recalculated the plan so that I could find all
> tasks assigned to them after their leaving date and then move the tasks to 
> a
> new resource.  Having done all this, I am still getting an overallocation
> error for the resource but can not find any remaining tasks after their
> leaving date.
>
> I've checked it over and over with different leaving dates and found that
> Project seems to think their is a task assigned at some time in early June
> next year, this however does not show up in any of the views.  I am now
> thinking that the database has some dud information in it that is causing
> the problem.
>
> My question therefore is: Is there a way of cleaning up the project file 
> to
> remove any bad information, or is there another possibility for this
> problem?
>
>
> Dave.
>
> 


Relevant Pages

  • Re: Non-Effort-Driven schedules
    ... Welcome to this Microsoft Project newsgroup:) ... You need to change the Task Type to Fixed Duration, ... work on it for 1 day and Resource R2 will work on it for 2 days. ... leaving a gap between the FS link from Task 1 and the start date. ...
    (microsoft.public.project)
  • Job offer in Portsmouth NH, USA
    ... I'm leaving a very nice job with a small company in the Portsmouth NH area ... very familiar with Excel and VBA. ... I swear on a stack of bibles that I'm not with some hiring agency, ... Again, I'm sorry this is not a question/answer about VBA, but I felt where ...
    (microsoft.public.excel.programming)
  • Overallocation in resource with no tasks!
    ... I've been trying to update a plan where one of my resources is leaving the ... I've changed their resource availability so that it ends on their ... thinking that the database has some dud information in it that is causing ...
    (microsoft.public.project2000)
  • Overallocation in resource with no tasks!
    ... I've been trying to update a plan where one of my resources is leaving the ... I've changed their resource availability so that it ends on their ... thinking that the database has some dud information in it that is causing ...
    (microsoft.public.project)
  • Re: just curious Xlpart xlWhole
    ... The xlwhole is the same as checking this box. ... xlpart is like leaving it ... VBA has a bunch of constants that are used instead of their numeric value (you ...
    (microsoft.public.excel.programming)

Quantcast