Easiest way ... export the time-scaled data in Excel, then use Excel to
sum the work for each resource then use Excel to draw that bar chart.

Hope this is useful to you. Let us know.

rms

parastoo mousavi wrote:
> I want to draw a graph that x axis is resource name and y axis is work of
> each resource. in the resource graoh and time scaled data in excel , i can't
> do that. is there any method to make it possible?



Relevant Pages

  • Re: graphical indicators
    ... the Excel forum about charting. ... But I do need to know, if the resource usage view works with the Gantt ... The assignment field for use in filtering once the data is in ...
    (microsoft.public.project)
  • Re: Resource Group vs Months in MSP Visual Reports
    ... It is still a manual process, but you can use the Grouping feature within the Excel Pivot table to apply your own groups and have the product subtotal. ... I don't believe there is an option for tweaking the Visual Report other than through Excel. ... Need Resource 'Group' in Visual Reports ...
    (microsoft.public.project)
  • Re: graphical indicators
    ... need in the Excel forum about charting. ... Assignment" at: ... side to the resource usage view, Jack Dahlgren has a macro called ...
    (microsoft.public.project)
  • Re: graphical indicators
    ... But I do need to know, if the resource usage view works with the Gantt chart ... from Project and now the problem is how to graph in Excel? ... The assignment field for use in filtering once the data is in ...
    (microsoft.public.project)
  • Re: graphical indicators
    ... from Project and now the problem is how to graph in Excel? ... Now I need to know graph this and project resource is very limited. ... The assignment field for use in filtering once the data is in ...
    (microsoft.public.project)