Re: Resource calendar *not* overriding Project calendar
From: Phyl (cdrivanova_at_gmail.com)
Date: 09/14/04
- Next message: Rob Schneider: "Re: Upgrade Question"
- Previous message: John: "Re: Does anyone have experience with MSP in VPC?"
- In reply to: Daniel Zitter - Matan Consulting: "Re: Resource calendar *not* overriding Project calendar"
- Messages sorted by: [ date ] [ thread ]
Date: 13 Sep 2004 20:39:20 -0700
Hi Daniel,
Actually, it *is* fixed duration. So, if we change it to fixed units
or fixed work, then it will work with the resource calendar? I'll try
that tomorrow ... when I'm in the office!
Thanks!
Phyl
"Daniel Zitter - Matan Consulting" <dzitter@matan.cc> wrote in message news:<D5C65518-F5D5-4F25-A68E-19A615739C84@microsoft.com>...
> Hi Phyl,
>
> Did you happen to change the Task Type to "Fixed Duration"? If you did than
> the project will use the project Calendar and not the resorces calendar.
>
> Hope this helps,
>
> Daniel
>
- Next message: Rob Schneider: "Re: Upgrade Question"
- Previous message: John: "Re: Does anyone have experience with MSP in VPC?"
- In reply to: Daniel Zitter - Matan Consulting: "Re: Resource calendar *not* overriding Project calendar"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|