Re: Predecessors!
From: JulieD (JulieD_at_hctsReMoVeThIs.net.au)
Date: 08/30/04
- Next message: Ralf: "Re: Resource Usage view: how display assigned rescources?"
- Previous message: JulieD: "Re: Charts in MS Project"
- In reply to: Steve House: "Re: Predecessors!"
- Next in thread: Ed Hanna: "Re: Predecessors!"
- Messages sorted by: [ date ] [ thread ]
Date: Mon, 30 Aug 2004 15:26:56 +0800
Hi Steve
good example ... but i seriously think you need to get out more :)
Cheers
JulieD
"Steve House" <sjhouse.remove.this@to.send.hotmail.com> wrote in message
news:eJLu%23kUjEHA.1764@TK2MSFTNGP10.phx.gbl...
> LOL Ain't it the truth! Last night I dreamt about that problem (have to
> stop with the pizza and salami just before bedtime) trying to figure out
> where linking the summary tasks might have a clear advantage and I came up
> with one. Imagine a project with 3 phases A, B, and C. The three phases
are
> such that all of A needs to be completed before B starts and all of B
> completed before C starts. A & C have several, say 5, subtasks under them
> that are linked within the phase FS. BUT phase B consists of 10 1 day
tasks
> that are completely arbitrary in the order in which they're done. Thus
> links to sequence them are superfluous and in fact in the scenario I'm
> developing they would be a negative. There is no predefined order of
tasks
> in B and no single task can be identified as the "first task" or the "last
> task" (yes I could put milestones in as subtasks as well and have one as a
> predecessor to all 10 activities and another as a successor to all 10 but
> that results in a spaghetti bowl of links). I assign resource Barney to
all
> the tasks in B. Resource leveling sequences out the tasks in B to set its
> duration. But how best to model its relationship to phases A & C? This
is
> one case where I think I'd use a link from Summary A to B and another link
> from B to summary C. One reason is that it does indeed preserve the
> arbitrary nature of the task sequencing in B as part of the model. We
don't
> care at all which subtask is done first, we 'll leave that to the
> resource(s) to decide for themselves. At that matters to us from a
> scheduling standpoint is how long it will take them to get all 10 done.
If
> we now acquire additional resource Fred who is also capable of doing those
B
> subtasks, we can substitute him for Barney on half of those tasks and when
> we re-level the duration of phase B and the start of phase C automatically
> adjusts without us having to worry about WHICH B level subtask each
resource
> is on or how we should rearrange the links. B gets done sooner so C can
> start earlier and that's all we need to deal with.
> --
> Steve House [MVP]
> MS Project Trainer/Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "Mark Durrenberger" <durrenm@yahoo.com> wrote in message
> news:e2JdylSjEHA.2932@TK2MSFTNGP10.phx.gbl...
> > "It depends" is the classic consultant answer :-)
> >
> > Mark
> >
> >
> > --
> > _________________________________________________________
> > Mark Durrenberger, PMP
> > Principal, Oak Associates, Inc, www.oakinc.com
> > "Advancing the Theory and Practice of Project Management"
> > ________________________________________________________
> >
> > The nicest thing about NOT planning is that failure
> > comes as a complete surprise and is not preceded by
> > a period of worry and depression.
> >
> > - Sir John Harvey-Jones
> > "Steve House" <sjhouse.remove.this@to.send.hotmail.com> wrote in message
> > news:OvcBRFGjEHA.1776@TK2MSFTNGP15.phx.gbl...
> > > Some people will argue to never link summary tasks while others will
say
> > > it's ok. I'd say, it depends <grin> - how's that for precise and
> > > definitive?). If Summary task A with all it's subtasks must be
finished
> > in
> > > it's entirety before any part of Summary task B begins AND if you know
> for
> > > sure which subtask in A will be the last one done and can identify the
> one
> > > task in B that will always be first, then you can link from the last
sub
> > in
> > > A to the first sub in B. If A and B have several parallel chains of
> tasks
> > > in each and you don't necessarily know in advance which task in A will
> end
> > > being the last one or whoch in B will end up being the first one, you
> > could
> > > link the two summaries. I've seem perfectly workable project plans
> using
> > > both methids, indeed, even using both methods in different parts of
the
> > same
> > > plan. The bottom line is what gives you the most readily understood
> > > schedule that serves as a valid predictive model of the project work
> > itself.
> > >
> > > --
> > > Steve House [MVP]
> > > MS Project Trainer/Consultant
> > > Visit http://www.mvps.org/project/faqs.htm for the FAQs
> > >
> > > "ak" <ak@discussions.microsoft.com> wrote in message
> > > news:9E64AEB9-9820-409B-BBB3-CAE8052F7D96@microsoft.com...
> > > > Hello,
> > > > My question is: Is it preferable to use summary tasks as
predecessor,
> > and
> > > > if not why?
> > >
> > >
> >
> >
>
>
- Next message: Ralf: "Re: Resource Usage view: how display assigned rescources?"
- Previous message: JulieD: "Re: Charts in MS Project"
- In reply to: Steve House: "Re: Predecessors!"
- Next in thread: Ed Hanna: "Re: Predecessors!"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|
|