Re: Fixing Start AND End Dates of tasks

From: Steve House (sjhouse.remove.this_at_to.send.hotmail.com)
Date: 07/29/04


Date: Thu, 29 Jul 2004 17:14:48 -0400

You really can't fix both start and end directly. In fact, you really
shouldn't be fixing any dates at all unless you are dragged kicking and
screaming into a constraint situation and simply have no other options. You
can get the effect of a fixed date at both ends, at least partially, by
making the task a fixed duration task and fixing the start date with a "Must
Start On" or "Must Start No Earlier Than" constraint. If the start was
fixed to 16 Aug and the duration was fixed to 5 days, that would mean the
end date would be 20 Aug. However that is not quite the same thing as
fixing the dates without regard to work or resources as editing can still
change duration and thus end date.

The situation I'd urge you to ponder is this: You may be saying that you
need to fix those dates because that's when you need to accomplish something
in order to meet your objectives and deadlines. But you need to be asking
whether it's even possible to do it then. Supposing parts aren't available
or the person doing the work is ill? Supposing the tasks that come before
it are delayed, what happens then? How do you KNOW it's even possible to
schedule that task on that date? By using Project and letting the dates be
calculated according the the according to precedence logic, precedence
duration, and resource availability Project can tell you if it is possible
to meet those dates and if the initial calculation says no, then you have a
model that you can use for "what-if" experimenting to get some idea of what
you have to tweak, re-arrange, or resources to juggle in order to make it
possible to meet your objectives. It's giving you some input into your
management processes about the proactive decisions you must make in order
manage the project so that it meets it goals. It'll only do that if you let
it do its job and do the calculations for which it is designed.

As I put it to my classes - you don't tell it the schedule you have, it
tells you the schedule you can get.

Hope this helps

-- 
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
"Helena" <Helena@discussions.microsoft.com> wrote in message
news:C1B1DB5E-1D1C-487D-96BB-C37B32F1918A@microsoft.com...
> Hi, I'm reasonably new to MSP, and have a need to fix the Start AND End
date of a task. Is there a way of doing this? All the available constraints
seem to apply to either one or the other....
>
> Many thanks.
> -- 
> H


Relevant Pages

  • Re: Calculating the duration between two custom date fields
    ... I started off putting the equation in a custom "duration" ... >Are the dates you are using the result of a calculation ... You can fix it by doing ...
    (microsoft.public.project2000)
  • Re: Damn Blizzard
    ... until Blizzard gets around to fixing the problem. ... Disconnects can equal 45 min queue. ... The code works fine, fix your computer. ... Public comments/complaints & direct complaints are a huge ...
    (alt.games.warcraft)
  • RE: [Full-Disclosure] Re: Full Disclosure != Exploit Release
    ... > wasn't important to fix. ... specific bug. ... and they wouldn't be fixing it as they are concentrating on supporting 32bit ... The information contained in this email and any attachments is ...
    (Full-Disclosure)
  • Re: Redirect
    ... Yes, and if it's garbage on purpose, don't fix it. ... And do you now understand that fixing 4 is just plain stupid? ... Suppose I want a password to be max 20 characters. ... > submitted data first. ...
    (comp.lang.php)
  • RE: [Full-Disclosure] Re: Full Disclosure != Exploit Release
    ... While I agree that they should be fixing their problems, ... >> wasn't important to fix. ... > specific bug. ... The information contained in this email and any attachments is ...
    (Full-Disclosure)