Re: Changing a Work Week for one Sub-task amongst many in Project 2000

From: John (mjensen_at_theriver.com)
Date: 07/29/04


Date: Wed, 28 Jul 2004 20:00:38 -0700


Dale,
Is your 24/7 operation perhaps a little heavy on management (i.e. 16
tasks for management and 2 for other workers) :-)

There are various ways to set up what you want depending on whether you
want the default calendar for the whole file to be 24/7 or 8/5. If you
want to treat the whole project as a 24/7/365 operation, go to
Tools/Change Working Time and set the calendar for "24 hours". Then go
to the Resource Sheet view and select resources that work 24/7 and make
sure their Base Calendar is "24 Hours". If not, select the 24 hour
calendar from the selection list that becomes visible when the Base
Calendar cell is activated. Next select all the management resources and
make sure their Base Calendar is set to "Standard".

For more information you might want to go to the MVP webpage at:
http://www.mvps.org/project/faqs.htm
and look at FAQ 5 - Default Working Hours

In addition, I suggest you go to Tools/Options/Calendar tab and hit the
Help button for more information.

Hope this helps.
John



Relevant Pages

  • RE: Resource Pool & Calendars
    ... I created a master project file with a custom calendar called ... "Master" with Monday through Friday as the working days. ... resources in ProjectA.mpp and assigned them the base calendar "Master" in the ...
    (microsoft.public.project)
  • Re: How to set up 24h project with P-T resources in multi time zones?
    ... base calendar for those London resources that shows the working day ... calendar to the resource. ... coverage over a 24 hour period. ...
    (microsoft.public.project)
  • Re: Changing a Work Week for one Sub-task amongst many in Project
    ... > want the default calendar for the whole file to be 24/7 or 8/5. ... > Tools/Change Working Time and set the calendar for "24 hours". ... > to the Resource Sheet view and select resources that work 24/7 and make ... > make sure their Base Calendar is set to "Standard". ...
    (microsoft.public.project)
  • Re: non-working days not taken into account for some tasks
    ... project calendar are being ignored for scheduling purposes. ... base calendar is the same as the project ... MS Project uses the "Standard" calendar as the base ... calendar for resources. ...
    (microsoft.public.project)
  • Re: OWA public Calendars
    ... a calendar in public folders is not an "active calendar"! ... "person" and has no "free/busy" management! ... You should create "resources" to manage correctly calendars... ... > I have OWA 2003 and ive got a public calendar set up in my public folders. ...
    (microsoft.public.exchange.applications)