Re: Is MS Project for my needs??? please help

From: Juststo (Juststo_at_discussions.microsoft.com)
Date: 07/27/04


Date: Tue, 27 Jul 2004 12:07:19 -0700

I actually have many stations all dependant on the previous station (an assembly line type outfit). Project seems like it would be usefull scheduling all of my projects with differnt delivery dates through all of my stations, but I will need to set up how many units/hr each station can accomodate in order for Project to properly schedule.

 Is there a simple way to do this with VBA or am I just asking for trouble?

"Jan De Messemaeker" wrote:

> Hi Justso,
>
> Although there are many aspects of your production schedule Project can help
> you with (I have supported a customer running a factory producing wooden
> prefab roofs) the questions you ask here are not out-of-the-box Project
> features.
>
> Project wil essentially help you when you have defined the elementary tasks
> a batch has to undergo, their duration and the sequence in which teh
> different tasks on each batch have to be executed
> Then you can introduce as many batches as you like using the same resources
> and ask Project for a feasible schedule. It will calculate one by postponing
> the tasks with the smallest priority (haw it defines that is an other
> discussion); so if the end result is unacceptable, you can play with the
> priorities or increase the capacity of the resources, e.g. by introducing
> overtime.
>
> Its strength lies in the aspect of combining teh sequence of the steps with
> capacity limitations.
> If on teh other hand you are running only one production step on one
> machine, Project's calculation features may not be what you are looking for.
>
> HTH
>
>
> --
> Jan De Messemaeker
> Microsoft Project Most Valuable Professional
> http://users.online.be/prom-ade/index.htm
> 32-495-300 620
> "Juststo" <Juststo@discussions.microsoft.com> wrote in message
> news:741D596F-B2FA-48C8-9B7C-939E8DDF8645@microsoft.com...
> > I run a woodworking manufacturing business and am having trouble getting
> the project demo to do what I need. Is there a way todo the following?
> >
> > I need to cut 400 boards. I have a saw that can cut 10 boards an hour. I
> need project to tell me how long the job will take. Is there a way to set
> up the total units a job needs to be complete and then define how many
> units/hr a resource can handle?
> >
> > Eventually I will integrate multiple jobs using the same resources and I
> want to know when I need to work overtime to meet deadlines.
> >
>
>
>



Relevant Pages

  • Re: custom report
    ... Jan De Messemaeker, Microsoft Project Most Valuable Professional ... For FAQs: http://www.mvps.org/project/faqs.htm ... does not have resources explicitly assigned to it. ...
    (microsoft.public.project)
  • Re: MS Project: Allow for employee termination
    ... overallocations and mayeb replac resources already. ... Jan De Messemaeker, Microsoft Project Most Valuable Professional ... I'm curious, though, about how most people use leveling. ...
    (microsoft.public.project)
  • Re: Using Team Resource
    ... From what I know the possibility to delegate in Server is set by the ... Jan De Messemaeker, Microsoft Project Most Valuable Professional ... There is no hierarchy in Project's resources. ...
    (microsoft.public.project)
  • Re: Levelling tasks with multiple resources
    ... said was it "appears" in other words when you do the levelling it 'doesn't ... "Jan De Messemaeker" wrote: ... First, and not relevant to the leveling issue, but annoying as well, Paul, ... Therefore I was hoping that when leveling resources I would get ...
    (microsoft.public.project)
  • Re: Sean Baker follow up (NDC)
    ... He was never in trouble that she knew of. ... nobody ever said they knew for a fact Sean was fired. ... If Sean was in trouble with his employer, ... He likely had a little conversation with Human Resources and management, and was told not to use company resources for Usenet anymore. ...
    (rec.music.gdead)