Re: SS Relationships
From: Steve House (sjhouse.remove.this_at_to.send.hotmail.com)
Date: 06/24/04
- Next message: Steve House: "Re: Tasks vs Activities"
- Previous message: Shaun: "Re: Allow Project to set Units"
- Messages sorted by: [ date ] [ thread ]
Date: Thu, 24 Jun 2004 15:15:43 -0400
Links always model the earliest time a task CAN start, not necessarily when
they WILL start. If A->C and B->C, both links SS, both A & B will need to
start before C can start since the first link says the earliest C can start
is when A is underway and and the second link says the earliest C can start
is when B has started. Can't really think of a way to model an either/or
relationship with C starting on the earlier of the two events
-- Steve House [MVP] MS Project Trainer/Consultant Visit http://www.mvps.org/project/faqs.htm for the FAQs "Dave Francis" <anonymous@discussions.microsoft.com> wrote in message news:EBF6C903-A3D7-4CCA-8D39-8501DE79EBD5@microsoft.com... > Is it possible for 2 tasks (A and B) to be link to a third (C) in such a way that C will start as soon as either A or B are started? > > You can use a SS relationship for one task, but what do you use for 2 or more tasks.