Re: Draw dependencies between rolled up milestones?

From: Mike Glen (glenATmvps.org)
Date: 06/23/04


Date: Wed, 23 Jun 2004 21:42:13 +0100

Hi Dave,

Welcome to this Microsoft Project newsgroup :-)

You can't link the rolled up part of the milestone, but if you expand the
summaries to show the milestones, you can link them as normal. Project will
then obey the link, though if you close down the summaries the link will not
appear.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :-))

Mike Glen
MS Project MVP

"Dave" <dgmoore@erols.com> wrote in message
news:8df3bf59.0406230939.166a1b0f@posting.google.com...
> Is there a way to draw a dependency line between a rolled up milestone
> on a summary bar and another rolled up milestone on a different
> summary bar? When I try to link two such tasks manually I get a link
> from the end of the first summary bar to the beginning of the other
> bar, but what I need is a link directly between the tasks.
>
> Thanks
> Dave

     



Relevant Pages

  • Re: Milestones & Predecessors
    ... try filtering for summaries and scan down the Predecessors column for ... I have a Circular Relationship error coming up in the project each ... How are you setting up the milestone? ...
    (microsoft.public.project)
  • Re: Using project as an outline
    ... Your Task 1 and Task 2 are Summaries, ... The headings and sub-headings are not the milestones. ... The milestone should come after the Tasks. ... Not that I think you really do want/need a diamond where a Summary Bar ...
    (microsoft.public.project)
  • Re: Milestones
    ... A summary task might mark the progress towards a milestone but the milestone proper is the instantaneous change of state that occurs when the summary is completed. ... If we're writing a program, it doesn't exist while we're writing. ... If your summaries correspond to deliverables, ...
    (microsoft.public.project)
  • Re: No task display unless I make it a subtask
    ... Hang on - you're saying "Roll Up To Summary" and "Hide Task Bar" is turned ... And I'm really confused with you inserting a subtask under a ... You might have a milestone included with the ... Summaries and milestones are just there ...
    (microsoft.public.project)
  • Re: Using project as an outline
    ... Your Task 1 and Task 2 are Summaries, ... The milestone should come after the Tasks. ... Not that I think you really do want/need a diamond where a Summary Bar ...
    (microsoft.public.project)