Re: Task 'unit' properties

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance

From: Mark 123 (none_at_none.com)
Date: 06/09/04


Date: Wed, 9 Jun 2004 13:26:22 +1200

This may be of some help too:

http://www.orbisoft.com/products/taskmanager/2005/support/faq.htm#QMainProject
http://www.orbisoft.com/kb/taskmanager/2005/q/1030.htm
http://www.orbisoft.com/download

"A Nony Mouse" <anony@mouse.org> wrote in message
news:%23fdwILWTEHA.3872@TK2MSFTNGP10.phx.gbl...
> Scott,
>
> Thanks for your post... I appreciate the offer of help, even from another
> 'newbie'. :)
>
> >I might also note that my personal
> > inclination would be to advise you to use something like
> > Access instead of MS Project if you plan to keep more than
> > very general information about the process.
>
> Agreed, but I am actually tracking specifics... Sorry if that was unclear
> in my previous post. I spent a couple weeks trying to figure out which
> product would do what I needed, and a PM tool seemed to fit the bill most
> appropriately.
>
> > All that I can advise here is that you take this into
> > consideration when making your time estimates.
>
> Hmmmm... That sucks. Thanks for your suggested fix, I can see how that
> works so at least I have an 'out' now. I just am surprised that Project
> doesn't have a means to allow for 'production' of a number of items...
> Essentially that's what we're trying to do.
>
> I have deadlines at sandwich in the processing and review time... My hope
> is that I could have an accurate picture of how far along we are between
> those deadlines and whether or not we need to shift certain landmarks
based
> on the resources we have available.
>
> I can do all the estimating up front... I was just hoping Project could
> recalculate on the fly once the 'real' numbers are in. I have been told
> that other PM suites (like Primavera) are supposedly capable of doing
> this...
>
> I really appreciate the help... I'll prolly shoot you an email just in
case
> you aren't leeping up with this thread anymore. And I might repost just
for
> kicks.
>
> Thanks so much,
> Brian
>
> "ScottB" <anonymous@discussions.microsoft.com> wrote in message
> news:1685901c44847$00a6dd30$a601280a@phx.gbl...
> > Let me preface my response by saying that I'm not far
> > ahead of you in terms of Project expertise...if you're so
> > inclined, feel free to post your message again
> > with 'second posting' added to the subject line since
> > people may not read this if they feel that it has already
> > been answered. (I'm the guy who submitted the question
> > just before yours). I might also note that my personal
> > inclination would be to advise you to use something like
> > Access instead of MS Project if you plan to keep more than
> > very general information about the process.
> >
> > In responding to your question, I'm assuming that you
> > probably don't have much latitude in terms of (a) calling
> > in additional resources to do the work and (b) moving
> > deadlines back. In this context, being able to 'show'
> > that more applications translates into the need for more
> > labor might be the program's best value for what you seem
> > to have in mind. Since each application is in itself a
> > task, one would be inclined to list each application this
> > way. Needless to say, setting this up complete with links
> > from one stage of the process to the next would quickly
> > turn into a paper nightmare.
> >
> > The way I would approach this is to meet with your team
> > and put their experience into writing in an effort to
> > figure out how long it takes a (one) person to process
> > applications along each step of the process. For example:
> > - Send out application package (20/day)
> > - Receive and review returned applications for
> > completeness (10/day)
> > - Review complete applications and separate out those not
> > meeting minimum standards (15/day)
> > - Set up interviews for those meeting minimal standards
> > (10/day)
> > - Conduct interviews (15/day)
> > - 'Score' applicants for second cut (30/day)
> > - Review short-list for acceptance (based on determined
> > acceptance levels) (15/day)
> > - Prepare and send out acceptance letters (30/day)
> > etc.
> >
> > I would then set these up as separate tasks. Then,
> > underneath each you could indent (making the above summary
> > lines) and create 'batches' with the understanding that
> > each batch covered, say, 100 applicants. For example:
> >
> > Send out applicant package ==============
> > Batch 1 ---
> > Batch 2 ---
> > Batch 3 ---
> > Receive and review... ============
> > Batch 1 ---
> > ...
> >
> > You could then link Batch 1 in one section with Batch 1 in
> > the next section. Similarly, Batch 1 in the first section
> > would be linked to Batch 2 in the same section. The
> > duration of each batch would be based on your earlier
> > discussions. For example, if a person could prepare 20
> > application packages in one day then Batch 1 would take 5
> > days (as would Batch 2 and 3). By following this
> > methodology you should get some sense of when Batch 1
> > would be completed, Batch 2 would be completed, etc.
> > This, of course, is somewhat simplistic since Batch 1
> > might start at 100 but be reduced to, say, 50 after the
> > first review, to 15 after the second review, etc. All
> > that I can advise here is that you take this into
> > consideration when making your time estimates. You would
> > insert or delete Batch numbers depending on how many
> > applications you actually receive.
> >
> > To the best of my knowledge, there is no easy way to
> > calculate and automate the durations along the lines that
> > you described. You might be better off with Excel or
> > something like that to derive level of efforts based on
> > variable inputs. Again, if it were me I would probably
> > use something other than MS Project if you want to be able
> > to track progress on each application. If this is the
> > case, feel free to contact me (shbellows@global4cit.com)
> > and I'll try to offer you some free advice to get you
> > headed in the right direction.
> >
> > I hope this helps and best of luck. Scott
> > >-----Original Message-----
> > >Hi all.
> > >
> > >I'm basically a Project newbie... I'm searched through
> > archived posts for
> > >this group and couldn't find an answer to this question.
> > >
> > >BACKGROUND: I work in an admissions office at a
> > college. We're using
> > >Project to manage the office deliverables from getting
> > applications in to
> > >getting decisions out.
> > >
> > >ISSUE: On an application deadline, the processing team
> > (that I oversee)
> > >begins to do all kinds of magic to each individual file.
> > The processing
> > >time for the whole batch depends on the total number of
> > applications we
> > >receive (more apps, more processing time). In addition,
> > another team in the
> > >office responsible for reviewing applications can only
> > begin work once we
> > >have processed a 'critical mass' of files for them.
> > >
> > >HOPE: We can set up our calendar based on estimated
> > inbound applications to
> > >start with. Once the actual application number is known,
> > we would love ot
> > >be able to change the 'input' number in Project and have
> > the calendar update
> > >automagically to reflect the real timeline.
> > >
> > >QUESTIONS:
> > >1) Is it possible to tell Project that a task's length
> > should be calculated
> > >based on (in this case) # of applications divided by
> > expected daily output?
> > >I would figure that this is a 'fixed work' task where
> > units would equal the
> > >number of applications, but I can't seem to nail down how
> > to set it up.
> > >
> > >2) Can you set a dependant task to begin once 100 'units'
> > of the other task
> > >have been completed? In my case, this would be setting
> > the reading/review
> > >of the applications to begin once ~100 applications have
> > been completely
> > >processed by my team.
> > >
> > >I look forward to reading your posted responses... And I
> > thank you *very
> > >very* much for your help!
> > >
> > >Sincerely, Mouse
> > >
> > >
> > >.
> > >
>
>



Relevant Pages

  • Re: Task unit properties
    ... > inclination would be to advise you to use something like ... I have deadlines at sandwich in the processing and review time... ... > applications along each step of the process. ... > each batch covered, say, 100 applicants. ...
    (microsoft.public.project)
  • RE: How many PCs are running dot net framework?
    ... Scott is asking a question that has been on my mind as well. ... reached the mainstream for client applications like it has for ASP code? ... be that 2.0 in coming and that will go mainstream but I am looking at a UI ... .NET framework would be prerequisite. ...
    (microsoft.public.dotnet.general)
  • Re: WG5-J3 Joint Meeting
    ... Gary L. Scott wrote: ... is co-arrays. ... to many applications. ...
    (comp.lang.fortran)
  • Re: Icon library
    ... "Scott J. Miles" wrote... ... a great collection - better suited (imo) to applications and ... entities rather than toolbars but with GlyFx and GlyFz (esp. ...
    (borland.public.delphi.thirdpartytools.general)
  • Re: Software for sale, anyone?
    ... > Hello Scott! ... > There was a surprising amount of games included also. ... "productivity" applications you've got? ...
    (comp.sys.ibm.ps2.hardware)