Re: best way to assign resources

From: Dale Howard [MVP] ("Dale)
Date: 05/12/04


Date: Wed, 12 May 2004 08:20:55 -0600

Lynne --

It sounds like you need to set the Task Type for all tasks in your project
to Fixed Work. When you do so, you can enter the Work and Duration, and
Microsoft Project will calculate the Units value automatically. If you
later change the Duration of a task, once again Project will recalculate the
Units. Hope this helps.

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"
"lynne baker" <lynnebkr@aol.com> wrote in message
news:1ca090a2.0405120316.52cc0713@posting.google.com...
> Hi all
> Project Pro 2002
> Server 2002
> PWA
>
> I'm sure this is such a basic issue, but some guidance from the
> experts would be very much appreciated.
> I have almost 300 tasks and about 8 resources.
> I would like to allocate tasks to these resources such that the
> application calculates what the percentage allocation is.
> At the moment we're doing it like this
> Create a task
> Allocate a resource
> Decide what percentage of the resource's time it might take
> decide how long it's going to take and enter it into duration
> decide how many hours effort is going to be required and enter it into
> work.
>
> Something tells me one of those steps is superfluous...
>
> And my resources are all horribly overallocated too!
>
> Ideally, what I'd like to do is keep the work the same, alter the
> duration to accommodate the amount of work, and calculate the
> percentage allocation automatically.
> Again, something tells me I'm asking for the moon!
>
> Many thanks for your help!


Relevant Pages

  • Re: Having the task finish date update when % complete = 100%
    ... Within Project Server there are ... option and so far all we have found is that if we have resources report % ... > versus duration required. ...
    (microsoft.public.project)
  • Re: best way to assign resources
    ... Here's how to speed up the assignment process: ... The above steps will position the Duration and Work columns side by side. ... ready to assign resources to each task, click the Assign Resources button on ... > I would like to allocate tasks to these resources such that the ...
    (microsoft.public.project)
  • best way to assign resources
    ... I'm sure this is such a basic issue, but some guidance from the ... I have almost 300 tasks and about 8 resources. ... I would like to allocate tasks to these resources such that the ... decide how long it's going to take and enter it into duration ...
    (microsoft.public.project)
  • Re: Task duration not netting when resources added.
    ... When you add resources to a task that has none attached, ... So even when you add both resources at once the duration ... To the contrary, when you allocate one resource, enter, then allocate a ... > nets to 8 hrs and SOMETIMES it stays at 16 hrs. I've tried to open NEW MS ...
    (microsoft.public.project)
  • problems with project.,...
    ... then assign 2 resources, the duration changes to 5 days. ... the task information sheet. ... >be done by both of us together so we allocate both of us ...
    (microsoft.public.project)

Loading