Re: Timescale in Hours and Minutes

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance

From: John (mjensen_at_theriver.com)
Date: 05/12/04


Date: Tue, 11 May 2004 19:45:44 -0700


David,
First go to Tools/Options View tab and select a Date Format that
includes time. Now when you enter a task Start date, you can also set
the hours and minutes. However, the idea of Project is not to manually
set Start and Finish times for tasks - it sets constraints and defeats
the purpose of using Project. Normally the Project Start date (and time
if desired) is set in Project/Project Information. The first task will
automatically start on the day and time. From then on, the Duration of a
task (can be minutes, hours, days, etc.) determines its Finish date and
linkages between tasks throughout the project plan sets all the
remaining Start and Finish dates. In some cases, it may be necessary to
directly enter the Start date for a particular task that is not
dependent on another task.

Hope this helps.
John



Relevant Pages

  • Re: Equation line numbers
    ... I use different margin settings for different kinds ... So setting the right tab for the equation number to 6 will not ... I checked the MathType Help file, and I didn't find any reference to ... To format the equation numbers, ...
    (microsoft.public.word.pagelayout)
  • Re: Question re jpeg compression
    ... David J Taylor wrote: ... Unless you have the uncompressed originals, you will gain nothing by saving what you already have in PNG format. ... I find that a low-compression JPEG is actually good enough for me. ... I don't have time to mess with processing "RAW" format images, and I believe in getting the exposure correct in the camera at the time of taking rather than fixing it later in post-processing. ...
    (rec.photo.digital)
  • Re: format of numbers in a downloaed file
    ... suggesting the extremely useful link of Mr David McRitchie as well as Mr. ... It took me time to understand the macro ... >> But some numbers are in a strange format neither as numbers, ... >> file and even not compatible to copy it in an excel spreadsheet. ...
    (microsoft.public.excel.misc)
  • Re: Corrupt Word Doc While Editing
    ... Word does not "auto format" your document unless you tell it to using ... On the AutoFormat As You Type tab, ... Disable this at on the Save tab of Tools | Options. ... Embedded graphics: When feasible, it is preferable to link the ...
    (microsoft.public.word.formatting.longdocs)
  • Re: Macro for inserting numbered equations-error
    ... included inserting the blank equation. ... NeoOffice and the ODF format. ... I would be tempted not to bother with a macro at all. ... I set a centering tab at the ...
    (microsoft.public.mac.office.word)