From: Jan De Messemaeker (jandemes)
Date: 03/11/04


Date: Thu, 11 Mar 2004 18:56:26 +0100

Hi Craig,

have a look at
http://www.mvps.org/project/faqs.htm
FAQ 37, Custom fields in Projects.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
"Craig" <anonymous@discussions.microsoft.com> schreef in bericht
news:1A069532-4F95-4B37-B43C-E69D5AFF0EC0@microsoft.com...
> Thanks for the input but...
> I actually already tried that.  The problem seems to be that I want to
group the specific field by "assignment" and Resource Group is the only
field that carries the value from the resource over to the assignments by
resource.  Therefore when I use "task" in my group, I recieve "no value" in
the view.  Is there another field that carries the same attributes as
Resource Group.  In otherwords, I can assign an attribute(external or
internal) to the field in the resource sheet and have that value associated
to the actual task assignments of the resources.
>
> The easiest way to explain it is:
>  If you input information in the "Group" field on the resource sheet, that
inforamtion is carried over to the Ghannt Chart under "Resource Group".  I'm
looking for another field that does the same.
>
> I'm experiencing this limitation both in MS Project 2002 and 2003.
>
> Thanks,
>  Craig
>
>
>
>
>      ----- Jan De Messemaeker wrote: -----
>
>      Hi Craig,
>
>      You can use any Text1-30 field and define a group (Project, New
Group) by
>      that field.
>      Works just as nicely as the Group field
>      HTH
>
>      --
>      Jan De Messemaeker
>      Microsoft Project Most Valuable Professional
>      Project Management Consultancy
>      Prom+ade BVBA
>      32-495-300 620
>      "Craig" <anonymous@discussions.microsoft.com> schreef in bericht
>      news:77D6EF6A-83BA-48A5-8190-033EEBC4A277@microsoft.com...
>      > Is there another "Resource Group" field.
>      > I need to utilize another "Resource Group" field but cannot find
one with
>      the same attributes.  I'm currently managing a project with many
external
>      vendors and need to both view the individual vendor forcasts and
actuals as
>      well as a rollup summary of all my external vendor costs.  I'm
currently
>      using the "Resource Group" field to categorize each vendor as
"External -
>      Vendor Name" vs. the Internal resources I have allocated to the
effort.
>      This allows me a nice view of my financial under the Resource
>      Usage(Cusomizable) view.  However, I need a nice rollup of all
external
>      figures for other reporting requirements.
>      >>


Relevant Pages

  • Re: Groups
    ... "Craig" schreef in bericht ... group the specific field by "assignment" and Resource Group is the only ... field that carries the value from the resource over to the assignments by ... well as a rollup summary of all my external vendor costs. ...
    (microsoft.public.project)
  • SUMMARY: TSM and Sun Cluster, or how to create a resource that is a script in Sun Cluster
    ... critical for me was to stop following the tsm manual where it was telling me ... If the script wasn't available on all ... nodes when I tried to create the resource, ... Each resource group is configured for failover operations. ...
    (SunManagers)
  • Sun Cluster 3.2 Errors
    ... *clresource: VALIDATE on resource RESOURCE-FAILOVER, ... Add a network resource to a resource group ... LogicalHostname or SharedAddress resource type. ... SUNW.GeoCtlAVS:1.0 GeoCtlAVS server for Sun Cluster ...
    (SunManagers)
  • Re: Separting costs for internal and external resources
    ... >> I can arrive at a partial answer using the Resource Group field in a task ... You may then add the Resource Group field to any task ... >> Group field) and then export that information to Excel. ...
    (microsoft.public.project)
  • [PATCH 03/12] Share Handling
    ... Provides functions to set/get shares of a specific resource of a resource ... disables resource group. ... * This involves checking shares between the child and its parent; ...
    (Linux-Kernel)