Re: Can we arrange the sequence of tasks instead of inputting the start-end time.
From: Mike Glen (glenATmvps.org)
Date: 02/24/04
- Next message: Dale Howard [MVP]: "Re: Can we arrange the sequence of tasks instead of inputting the start-end time."
- Previous message: Mike Glen: "Re: What is use of SQLServer in MS Project Server Collaboration Environment"
- In reply to: Jie: "Can we arrange the sequence of tasks instead of inputting the start-end time."
- Next in thread: Dale Howard [MVP]: "Re: Can we arrange the sequence of tasks instead of inputting the start-end time."
- Messages sorted by: [ date ] [ thread ]
Date: Tue, 24 Feb 2004 20:37:25 -0000
Hi Jie,
Welcome to this Microsoft Project newsgroup :-)
Yes indeed, that is the correct way and Project is designed to work that
way! You might like to see FAQ Item: 42. Guide to Network Analysis
FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/
Hope this helps - please let us know how you get on :-)
Mike Glen
Project MVP
Jie wrote:
> Can we arrange the sequence of tasks instead of inputting the
> start-end time?
>
> Our project is just a Nation Science Foundation project. So we can
> not know the end time of each task. but we know the sequence of each
> task. Can we arrange the sequence of tasks instead of inputting the
> start-end time?
>
> Thanks!
- Next message: Dale Howard [MVP]: "Re: Can we arrange the sequence of tasks instead of inputting the start-end time."
- Previous message: Mike Glen: "Re: What is use of SQLServer in MS Project Server Collaboration Environment"
- In reply to: Jie: "Can we arrange the sequence of tasks instead of inputting the start-end time."
- Next in thread: Dale Howard [MVP]: "Re: Can we arrange the sequence of tasks instead of inputting the start-end time."
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|