Zero Resource contribution to a task

From: Conrad Santiago (anonymous_at_discussions.microsoft.com)
Date: 02/19/04


Date: Thu, 19 Feb 2004 12:01:07 -0800

What is the best way to show this situation?

We are training a new resource, let's call him Newbie. He will be riding shotgun on a task assigned to an experienced resource, let's call him Joe Pro.
I want to assign Newbie to the same task as Joe Pro, however, Newbies's contribution to the task will be nil. This way, it will show him scheduled on that task, but he won't be affecting the duration.

What I did was assigned them both to the same task. However, I can't keep Newbie from affecting the duration, even though, he is set to 0% Units. I suppose I could double the work, however, that isn't true either.

Any ideas?

Thanks!



Relevant Pages

  • Re: Zero Resource contribution to a task
    ... Resource: Joe Pro ... > We are training a new resource, let's call him Newbie. ... but he won't be affecting the duration. ...
    (microsoft.public.project)
  • Re: Dangerous E-mails.
    ... >(I think it is things like HTA files, Active X and Javascript, etc). ... >Does anyone know of a good resource where I can (as a newbie) learn more ...
    (alt.computer.security)
  • Re: Calculate effort for a short duration task between dates
    ... Yes I am a newbie but willing to learn. ... say it is best suited to sequencing the needed tasks. ... me as a resource for 25% of the time but not have the 1 day ... task time change if I adjust my resource time up to 50% from 25%? ...
    (microsoft.public.project)
  • Re: insert names of all pages in visio drawing
    ... I'm a newbie, so ... can you please point me to a resource that explains how to put that code to ... Prev by Date: ...
    (microsoft.public.visio.developer)
  • Custom fields with duration to show contingency
    ... I'm a newbie with MS Project, and have just started to use custom ... calculate the duration and cost of each project task, ... As such, I'm trying to multiply the duration, work, start and finish ...
    (microsoft.public.project2000)