Re: what does "Scheduling ignores resource calenders" mean?
From: Jan De Messemaeker (jandemes)
Date: 02/15/04
- Next message: John Beamish: "Re: Fill down on recurring tasks acts weird!?"
- Previous message: Arthur: "Re: MS Project 2003 Demo"
- In reply to: Jie: "what does "Scheduling ignores resource calenders" mean?"
- Next in thread: Jie: "RE: what does "Scheduling ignores resource calenders" mean?"
- Messages sorted by: [ date ] [ thread ]
Date: Sun, 15 Feb 2004 11:35:03 +0100
Hi Jie,
I only get that checkbox when assigning a task calendar to a task (in fact I
only see it in Task Information, Advanced)
There its meaning is as follows:
When you assign to a task both a resource and a task calendar, Project will
schedule the task when both the task calendar and the resource calendar show
working time.
When however this box is checked the task will be scheduled based on the
task calendar only.
For instance, Resource Calendar is normal 5/7, Task Calendar is 7/7
When the box is checked a 3 day task starting on Fr morning ends on Su night
When not, it ends on Tue night
HTH
-- Jan De Messemaeker Microsoft Project Most Valuable Professional Project Management Consultancy Prom+ade BVBA 32-495-300 620 "Jie" <wrider03@hotmail.com> schreef in bericht news:7E6216D1-962B-4C71-ABD4-729507584277@microsoft.com... > Friends, > > When I was setting the calender of my project to a new calender, there is an checkbox. The content of this checkbox is "Scheduling ignores resource calenders" . What if I check it? > > Thanks!
- Next message: John Beamish: "Re: Fill down on recurring tasks acts weird!?"
- Previous message: Arthur: "Re: MS Project 2003 Demo"
- In reply to: Jie: "what does "Scheduling ignores resource calenders" mean?"
- Next in thread: Jie: "RE: what does "Scheduling ignores resource calenders" mean?"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|