Re: Administrative Projects in Project Pro and PWA
- From: "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com>
- Date: Wed, 8 Mar 2006 19:03:51 -0700
Matt --
In the future, please post your Project Server questions to the
microsoft.public.project.server newsgroup, as this newgroup is closing down.
To answer your question, no, this is not possible. Even after you create
Rules, you must still click the Run Rules Now button to run them. This is
because Microsoft made an assumption that you must be at least minimally
involved with the updates process. Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
<wegz@xxxxxxxxxxxxxxxx> wrote in message
news:1141869343.920580.152820@xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
Hello.
I have set up an administrative project called non-project time that
allows staff to enter time against holidays, non-project events and
project meetings.
When staff send updates for regular tasks, the updates go for approval
to that Projects PM, where the PM accepts the updates in PWA, then
updates the progress in Project Pro before re-publishing the project.
Now I totally understand how that works and am happy with it.
My problem is with the same process happening with the non-project time
project. When staff enter time for holidays or meetings or non project
events, all their updates get sent to me for approval. Which is ok at
the moment because its only 30 people, but we are planning to roll out
to quite a lot more staff soon and I don't want to be bombarded with
continually having to update peoples times etc.
It was decided that it would be acceptable for time entered into this
admin project to automatically update without needing anyone to accept
or deny (we are a trusting lot!!)
I set up a rule in PWA though the Updates page --> selecting 'set rules
for automatically accepting changes' from the side pane. I set the rule
to update for all task updates for that project from all resources...
The rule is enabled but all updates still come to me in the updates
page of PWA for approval and are not automatically updated.
Is there any way to get around this so we can just have all information
from this admin project just automatically update. Basically a set and
forget???
Thanks to anyone who read this far and anyone who can help.
Matt
.
- References:
- Prev by Date: Administrative Projects in Project Pro and PWA
- Next by Date: Re: MSP server 2002 vs 2003
- Previous by thread: Administrative Projects in Project Pro and PWA
- Index(es):