Need Feedback on Resource Management



I'm heading a project to enhance our use of Project Pro to include resource
management. We've been using Project Pro since Jan '05 primarily as a time
tracking tool (only actuals). We have huge inconsistencies in how projects
are set up and managed (some currently end in 2049) so we know we have some
training issues to tackle. Aside from that we need project managers to be
more specific in assigning tasks loads and having users update ETC. We
currently have approx 400 projects in play.

Have any other Project Pro installations gone down this path? What were your
major hurdles? What level of success did you attain? How much impact was it
on your project managers/users?
.



Relevant Pages

  • Re: Where is "paragraph #9"
    ... be held accountable for permit non-compliance and resource damage. ... I believe that the objectives set for the overall management of the ... Incident Management Team, Forest and cooperating agencies. ...
    (alt.gathering.rainbow)
  • Re: Where is "paragraph #9"
    ... be held accountable for permit non-compliance and resource damage. ... I believe that the objectives set for the overall management of the ... Incident Management Team, Forest and cooperating agencies. ... Mapping Social Change: A Visualization Method Used in the Monongahela ...
    (alt.gathering.rainbow)
  • Re: Resource Allocation Issue
    ... etc - of project management are far more important than any software you ... > where all the resource can be identify via a head count. ... >> qualified to do the job, their maximum allocation is 700%. ... >> allocate the Network Services resource to the task at 400%. ...
    (microsoft.public.project)
  • Re: Resource Allocation Issue
    ... > managerial soft skills - organizational, political, requirements ... > etc - of project management are far more important than any software you ... > they plan ... >> where all the resource can be identify via a head count. ...
    (microsoft.public.project)
  • Re: Resource allocation across multiple projects
    ... the specific breakdown on hours and time ... overallocated because I have left the resource units at 100%. ... contracts that know very little about project management. ... fellow MVP, Mike Glen's series on Project lessons and techniques. ...
    (microsoft.public.project)