Re: Enterprise Resource Pool issue

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Dale, you are a correct, but one note, my username had both allow and deny
deselected, but I could not edit the GRP until I explicitly check the allow
box.
Is that meaning that somewhere there are permissions that are customized
that may be overwriting the defaults?

-thanks



"Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts.com> wrote in
message news:%23vbNSmoSFHA.2964@xxxxxxxxxxxxxxxxxxxxxxx
> richierich --
>
> Are you a member of multiple Groups in Project Server, or are you a member
> of only the Administrators group? If you are a member of multiple Groups,
> then I would suspect that the "Edit enterprise resource information"
> permission has been set to Deny for one of the Groups in which you are a
> member and which has access to the resources in the My Organization
> category. Here's how you could diagnose this particular situation:
>
> 1. Log into PWA with administrator permissions
> 2. Click Admin - Manage security
> 3. Select the My Organization category and click the Modify Category
> button
> 4. In the Users and groups section, select a Group in which you are a
> member
> 5. Examine the "Edit enterprise resource information" permission in the
> Permissions grid
> 6. If it is set to Deny, deselect this option and leave both the Allow
> and Deny checkboxes deselected
> 7. Repeat steps #4-6 for each Group in which you are a member
> 8. Click the Save Changes button
>
> Just a thought. Perhaps the others will have some ideas for you also.
> Hope this helps.
>
> --
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> Denver, Colorado
> http://www.msprojectexperts.com
> "We wrote the books on Project Server"
>
>
> "richierich" <rsr2564@xxxxxxxxxxx> wrote in message
> news:uAP8CLgSFHA.248@xxxxxxxxxxxxxxxxxxxxxxx
>>I am unable to edit my Global Enterprise Resource Pool from the Project
>>Pro 2003 app. I am running Project Server 2003. I have all administrator
>>rights and there is one user who can edit the resource pool, but the rest
>>of us cannot.
>>
>> Please Help
>>
>> thanks
>>
>
>


.



Relevant Pages

  • "What Thaksin had done wrong"
    ... Corruption in the construction of railway Airport Link ... Quick Edit ... Member No.: 5,801 ... Posts: 901 ...
    (soc.culture.malaysia)
  • Re: OT: debug and compiling doesnt work right
    ... The ability of VC to do a compile-and-go is limited. ... member or method, or change the type of a data member or result or arguments of a method, ... Database For Edit and Continue". ... you will get the message about needing to recompile. ...
    (microsoft.public.vc.mfc)
  • Re: Using VC++ from a C++Builder perspective
    ... > and then set its properties to edit it. ... MFC control objects have almost no member variables. ... language API callbacks and C++ member functions. ...
    (microsoft.public.vc.ide_general)
  • Using VC++ from a C++Builder perspective
    ... By that I mean that in Builder you ... can programmatically create a new object (like an Edit box), ... Builder, Top, Left, Width, etc. are member "properties" which act like ... about whether you are directly setting them or whether they are actually ...
    (microsoft.public.vc.ide_general)
  • sshd_config and ssh2d_config
    ... I have tried to edit the sshd_config and the ssh2d_config files to ... I then killed the sshd2 daemon and restarted it. ... was still able to login from the computer I tried to deny. ... restarting it is ok too. ...
    (comp.security.ssh)