RE: Copying a Baseline to another Baseline

Tech-Archive recommends: Fix windows errors by optimizing your registry

From: Bob (bob.mcaninch_at_honeywell.com)
Date: 01/10/05


Date: Mon, 10 Jan 2005 10:39:04 -0800

To answer my own question ....
I set up a Variance view showing Baseline Start and Baseline Finish. In this
view, I inserted columns for Baseline10 Start and Baseline10 Finish. Then
copy the field values from Baseline to Baseline10.

Don't know why I didn't think of this earlier. Vapor lock I suppose.

Bob

"Bob" wrote:

> We've decided to save our original baseline as Baseline10. Several weeks ago,
> one of our PM's accidentally saved it as Baseline(0). How can I copy it to
> Baseline10 now?
>
> Thanks,
> Bob