RE: Percent complete not populating

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance

From: Michelle (MIchelle_at_discussions.microsoft.com)
Date: 01/10/05


Date: Mon, 10 Jan 2005 07:21:53 -0800

Thanks for your reply. There are situations in which the
PM needs to zero out the remaining work to support a
particular development methodology that works in
iterations. If a task isn't completed in a certain
iteration the original task is zero'd out and then a new
task in the new iteration is added with the remaining work
added to the work. The way I understand project to work
when remaining equals zero the task should be marked 100%,
correct? Professional isn't doing this though. The PM
has to mark the task 100% after putting the remaining work
to zero.
Any thoughts?

 
>-----Original Message-----
>The PM shouldn't have to zero out remaining work in Pro.
If you open the
>Plan in Pro and insert the column Actual Work Protected,
you can see the data
>that is 'transferred' from the users entering time in
PWA. In time***
>view, they should be entering their actual work each day
for a given task.
>Have you looked at the resources assigned to the task's
timesheets to
>validate they're entering actuals and remaining work is
adjusted accodingly?
>That is pertinent data that is exchanged between PWA and
Pro. Another thing
>to look at is if you have automatic resource leveling
turned on/off.
>
>"Michelle" wrote:
>
>> I have a project manager whom after receiving updates
from
>> PWA wants to put the remaining work for a task to
zero.
>> The problem that is occuring is that after he zero's
out
>> this remaining work the percent complete is not
changing
>> to 100%. Does anyone have any ideas as to why this is
>> doing this? Is he missing a step that will
automatically
>> mark this task as 100%?
>>
>> Also as part of the team's weekly status meeting they
>> review the updates to the plan and then assign any new
>> tasks that have been added to a certain week. After
the
>> task assignments are completed the project manager
saves
>> the plan and publishes. The team then reviews all
>> assignments for the next week in the resource
assignment
>> view in PWA. The problem is that after the PM
publishes
>> the assignments the resources and the project manager
then
>> only see a portion of the assignments in the resource
>> assignment view in PWA. Any idea why this is doing
this?
>>
>> Thanks!
>> Michelle
>>
>>
>.
>