Re: Let Resource Change Field on Timesheet - Actual Start/Finish
From: Dale Howard [MVP] ("Dale)
Date: 12/18/04
- Next message: Dale Howard [MVP]: "Re: Any way to set project to auto publish all projects?"
- Previous message: Mike Glen: "Re: Resource % Allocation"
- In reply to: Scott Button: "Re: Let Resource Change Field on Timesheet - Actual Start/Finish"
- Messages sorted by: [ date ] [ thread ]
Date: Sat, 18 Dec 2004 09:49:12 -0700
Scott --
If a resource assigns himself to a task, the PM must approve the assignment
before he can enter actuals on the task. Perhaps that explains your
situation. Thanks for following up with how you solved the problem. :)
-- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Scott Button" <ScottButton@discussions.microsoft.com> wrote in message news:71312B2B-ECD3-4898-B892-FCADEA8950DB@microsoft.com... > > I re-published a project from scratch, and it worked this time. In the > process, I made myself an Enterprise resource, and I think I was not > before. > I was self-assigning the task through PWA, and this may have prevented the > actual start/finish from having edit enabled. > > Thanks for the help and encouragement, Dale. > > Scott.
- Next message: Dale Howard [MVP]: "Re: Any way to set project to auto publish all projects?"
- Previous message: Mike Glen: "Re: Resource % Allocation"
- In reply to: Scott Button: "Re: Let Resource Change Field on Timesheet - Actual Start/Finish"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|