Re: Error messages in Event viewer when publishing projects..Please Help
From: Dale Howard [MVP] ("Dale)
Date: 11/20/04
- Next message: David: "Pop-UP authentication window when connect PWA"
- Previous message: Dale Howard [MVP]: "Re: force check-in resource"
- In reply to: Cory Craig: "Error messages in Event viewer when publishing projects..Please Help"
- Next in thread: Cory Craig: "Re: Error messages in Event viewer when publishing projects..Please Help"
- Reply: Cory Craig: "Re: Error messages in Event viewer when publishing projects..Please Help"
- Messages sorted by: [ date ] [ thread ]
Date: Sat, 20 Nov 2004 14:24:34 -0700
Cory --
The error means that you have one or more local resources in your project.
A local resource is a non-enterprise resource that does not exist in the
Enterprise Resource Pool. The solution to this problem is to do the
following:
1. Open the project
2. Apply the Resource *** view
3. Double-click the first local resource (indicated by the twin heads
indicator)
4. Set the Workgroup value to None
5. Click OK
6. Repeat this process for each local resource
7. Save and republish the project
Hope this helps.
-- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Cory Craig" <cory.craig@integris-health.com> wrote in message news:34cd2306.0411191347.7b6bc2a8@posting.google.com... > Can anyone help with these error messages I am seeing in our PS 2003 > environment. Running OS2003 and MS server 2003 SP1. > > > Event Type: Error > Event Source: Microsoft Project Server Tracing Eventlog Provider > Event Category: None > Event ID: 2 > Date: 11/19/2004 > Time: 3:28:42 PM > User: NT AUTHORITY\LOCAL SERVICE > Computer: 3SBMD9D > Description: > Component: PjMsgHlr > File: > C:\Office\devsp\project\WebClient\source\server\pjmsghlr\MsgHandler.cpp > Line: 588 > Error Number: 0x8c040017 > Description: <Description><![CDATA[Assert Detected. The error code was > also included.]]></Description> > > > Event Type: Error > Event Source: Microsoft Project Server Tracing Eventlog Provider > Event Category: None > Event ID: 2 > Date: 11/19/2004 > Time: 3:28:42 PM > User: NT AUTHORITY\LOCAL SERVICE > Computer: 3SBMD9D > Description: > Component: PjMsgHlr > File: > C:\Office\devsp\project\WebClient\source\server\pjmsghlr\MsgHandler.cpp > Line: 1100 > Error Number: 0x8c040017 > Description: <Description><![CDATA[Assert Detected. The error code was > also included.]]></Description> > > > Component: PjMsgHlr > File: > C:\Office\devsp\project\WebClient\source\server\pjmsghlr\updatedb.cpp > Line: 2264 > Error Number: 0x8c040017 > Description: <Description><![CDATA[Assert Detected. The error code was > also included.]]></Description> > > And from earlier 11/18/2004 > ------------------------------------------------------------------------- > Component: PjSvrUtl > File: > C:\Office\devsp\project\WebClient\source\server\pjsvrutl\PjENAgent.cpp > Line: 525 > Error Number: 0x8004020f > Description: <Description><![CDATA[Assert Detected. The error code was > also included.]]></Description> > > File: C:\Office\devsp\project\WebClient\source\utility\pjsmtpemail.cpp > Line: 400 > Error Number: 0x8004020f > Description: <Description><![CDATA[Assert Detected. The error code was > also included.]]></Description> > ___________________________________ > > Description: <Description><![CDATA[The server rejected one or more > recipient addresses. The server response was: 501 5.5.4 Invalid > Address > ]]></Description> > > > Component: PjMsgHlr > File: > C:\Office\devsp\project\WebClient\source\server\pjmsghlr\MsgHandler.cpp > Line: 588 > Error Number: 0x8c040017 > Description: <Description><![CDATA[Assert Detected. The error code was > also included.]]></Description> > > Someone Please Help!! > > Thank You > Cory Craig
- Next message: David: "Pop-UP authentication window when connect PWA"
- Previous message: Dale Howard [MVP]: "Re: force check-in resource"
- In reply to: Cory Craig: "Error messages in Event viewer when publishing projects..Please Help"
- Next in thread: Cory Craig: "Re: Error messages in Event viewer when publishing projects..Please Help"
- Reply: Cory Craig: "Re: Error messages in Event viewer when publishing projects..Please Help"
- Messages sorted by: [ date ] [ thread ]