Cory,

You can find a description of the error in the Administrators Guide (pg.
326). The error title is "Manager Not Allowed to Create a New Account." Has
the project server administrator denied the "Create Accounts from Microsoft
Project" permission?" If so, then you are likely saving a project to the
server with new resources that are set to use the project server Workgroup
setting (or default).

Hope this helps,

John

"Cory Craig" wrote:

> Can anyone help with these error messages I am seeing in our PS 2003
> environment. Running OS2003 and MS server 2003 SP1.
>
>
> Event Type: Error
> Event Source: Microsoft Project Server Tracing Eventlog Provider
> Event Category: None
> Event ID: 2
> Date: 11/19/2004
> Time: 3:28:42 PM
> User: NT AUTHORITY\LOCAL SERVICE
> Computer: 3SBMD9D
> Description:
> Component: PjMsgHlr
> File: C:\Office\devsp\project\WebClient\source\server\pjmsghlr\MsgHandler.cpp
> Line: 588
> Error Number: 0x8c040017
> Description: <Description><![CDATA[Assert Detected. The error code was
> also included.]]></Description>
>
>
> Event Type: Error
> Event Source: Microsoft Project Server Tracing Eventlog Provider
> Event Category: None
> Event ID: 2
> Date: 11/19/2004
> Time: 3:28:42 PM
> User: NT AUTHORITY\LOCAL SERVICE
> Computer: 3SBMD9D
> Description:
> Component: PjMsgHlr
> File: C:\Office\devsp\project\WebClient\source\server\pjmsghlr\MsgHandler.cpp
> Line: 1100
> Error Number: 0x8c040017
> Description: <Description><![CDATA[Assert Detected. The error code was
> also included.]]></Description>
>
>
> Component: PjMsgHlr
> File: C:\Office\devsp\project\WebClient\source\server\pjmsghlr\updatedb.cpp
> Line: 2264
> Error Number: 0x8c040017
> Description: <Description><![CDATA[Assert Detected. The error code was
> also included.]]></Description>
>
> And from earlier 11/18/2004
> -------------------------------------------------------------------------
> Component: PjSvrUtl
> File: C:\Office\devsp\project\WebClient\source\server\pjsvrutl\PjENAgent.cpp
> Line: 525
> Error Number: 0x8004020f
> Description: <Description><![CDATA[Assert Detected. The error code was
> also included.]]></Description>
>
> File: C:\Office\devsp\project\WebClient\source\utility\pjsmtpemail.cpp
> Line: 400
> Error Number: 0x8004020f
> Description: <Description><![CDATA[Assert Detected. The error code was
> also included.]]></Description>
> ___________________________________
>
> Description: <Description><![CDATA[The server rejected one or more
> recipient addresses. The server response was: 501 5.5.4 Invalid
> Address
> ]]></Description>
>
>
> Component: PjMsgHlr
> File: C:\Office\devsp\project\WebClient\source\server\pjmsghlr\MsgHandler.cpp
> Line: 588
> Error Number: 0x8c040017
> Description: <Description><![CDATA[Assert Detected. The error code was
> also included.]]></Description>
>
> Someone Please Help!!
>
> Thank You
> Cory Craig
>



Relevant Pages

  • Re: Project Server 2007 - Post Install
    ... Partners to assist with the implementation of Project Server 2007 and to do ... for Project Web Access. ... Enter a friendly name for the login account, ... set up AD synchronization to populate your Enterprise Resource Pool ...
    (microsoft.public.project)
  • Re: Access server using PP and domain account
    ... Thanks for all the info Earl. ... you to be on a M$ network. ... building yet I'm successfully connecting to a project server on another ... > that it's a trusted site with automatically log in using windows account ...
    (microsoft.public.project.pro_and_server)
  • Re: Timetracking
    ... Dale A. Howard ... "We wrote the book on Project Server" ... > I just finished changing a testing account I have from Windows ... >> When you change the PWA user account to Project Server authentication, ...
    (microsoft.public.project.pro_and_server)
  • Re: Access server using PP and domain account
    ... the credentials you use to login to the workstation. ... > - user account on project server is set to use windows authentication ...
    (microsoft.public.project.pro_and_server)
  • Re: problems with resources and collaboration
    ... You now need to create the Project Server account in the Project client by ... With regard to your resource issue, ... >> enterprise options> Import Resources to Enterprise Resource pool. ...
    (microsoft.public.project.pro_and_server)