Re: THOUSANDS of extra Resources added
From: Dale Howard [MVP] ("Dale)
Date: 11/16/04
- Next message: Dale Howard [MVP]: "Re: Bloc cost information to Project managers"
- Previous message: Dale Howard [MVP]: "Re: how can i setup a view for executives to see status of project"
- In reply to: Randy: "Re: THOUSANDS of extra Resources added"
- Next in thread: Gary L. Chefetz \(MVP\): "Re: THOUSANDS of extra Resources added"
- Messages sorted by: [ date ] [ thread ]
Date: Tue, 16 Nov 2004 15:33:36 -0700
Randy --
In the future, I would strongly recommend that you import non-enterprise
projects using the Import Wizard. Without looking at your database, I
cannot be certain what is happening, and whether you have database
corruption. However, when you receive a solution from Microsoft, would you
be kind enough to share the results with the rest of the group? Thanks in
advance.
-- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "Randy" <Randy@discussions.microsoft.com> wrote in message news:B9B266A5-AAE2-4ACF-8DAC-453A651D9852@microsoft.com... > Dale, > > No, we did not use the import option. When the file is not on the PS we > were taught to open the file and then use the Save Online option to get > the > project on the server. These plans were originally built offline using > MSP > 2003 Pro because we did not have the PS built and online before they > needed > to get the plans created. We have now opened a case with MS regarding > this > so we will see what they come up with. > > Randy > > "Dale Howard [MVP]" wrote: > >> Randy -- >> >> You did not answer my last question. Did you use Tools - Enterprise >> Options - Import Project to Enterprise to import the projects into >> Project >> Server? Or did you merely open the .mpp file and click File - Save As. >> If >> you did the latter, this might be the source of your problem, as this is >> not >> the correct procedure for brining a non-enterprise project into Project >> Server. >> >> In addition, why in the world are your PM's creating .mpp files in the >> first >> place? Why don't they log into Project Server, create a new project, and >> then populate the project team with enterprise generic or human >> resources? >> >> -- >> Dale A. Howard [MVP] >> Enterprise Project Trainer/Consultant >> http://www.msprojectexperts.com >> "We wrote the book on Project Server" >> >> >> "Randy" <Randy@discussions.microsoft.com> wrote in message >> news:F6DDC0D8-18E1-4F3D-BA67-F5D6DBDD1B54@microsoft.com... >> > Dale, >> > >> > The plans were opened from file and then saved online. Then the >> > generic >> > resources were replaced with enterprise resources. Someone has told me >> > that >> > the plans may be corrupt. If that's the case, how do we fix them? >> > >> > Randy >> > >> > "Dale Howard [MVP]" wrote: >> > >> >> Randy -- >> >> >> >> When you say "created offline with generic local resources and then >> >> brought >> >> online", are you importing the project using Tools - Enterprise >> >> Options - >> >> Import Project to Enterprise and then replacing the local generic >> >> resources >> >> with enterprise resources? >> >> >> >> -- >> >> Dale A. Howard [MVP] >> >> Enterprise Project Trainer/Consultant >> >> http://www.msprojectexperts.com >> >> "We wrote the book on Project Server" >> >> >> >> >> >> "Randy" <Randy@discussions.microsoft.com> wrote in message >> >> news:35CA4AFE-615B-4B9A-B2B9-F4D0BE69BAA9@microsoft.com... >> >> > Dale, >> >> > >> >> > Can you clarify what a shared resource pool means? These plans were >> >> > all >> >> > created offline with generic local resources and then brought >> >> > online. >> >> > When >> >> > the replication of resources happens, it is always a generic (local) >> >> > resource >> >> > that replicates. >> >> > >> >> > Randy >> >> > >> >> > "Dale Howard [MVP]" wrote: >> >> > >> >> >> Randy -- >> >> >> >> >> >> In the pre-Project Server days when organizations used a shared >> >> >> resource >> >> >> pool, the behavior your describe indicated database corruption. >> >> >> >> >> >> -- >> >> >> Dale A. Howard [MVP] >> >> >> Enterprise Project Trainer/Consultant >> >> >> http://www.msprojectexperts.com >> >> >> "We wrote the book on Project Server" >> >> >> >> >> >> >> >> >> "Randy" <Randy@discussions.microsoft.com> wrote in message >> >> >> news:791AE49B-A280-430A-B793-6906D0B6CF18@microsoft.com... >> >> >> > We are running MSP 2003 Pro and are having a problem with extra >> >> >> > resources >> >> >> > somehow being added to the plans. These additional resources are >> >> >> > local >> >> >> > generic resources and when this happens the number of resources >> >> >> > jumps >> >> >> > to >> >> >> > 40 - >> >> >> > 50,000!! At this point we cannot make any changes to the plan >> >> >> > until >> >> >> > we >> >> >> > take >> >> >> > it offline, delete the resources, save and then bring it back >> >> >> > online. >> >> >> > Anyone >> >> >> > know what is causing this? >> >> >> > >> >> >> > Randy >> >> >> >> >> >> >> >> >> >> >> >> >> >> >> >> >> >>
- Next message: Dale Howard [MVP]: "Re: Bloc cost information to Project managers"
- Previous message: Dale Howard [MVP]: "Re: how can i setup a view for executives to see status of project"
- In reply to: Randy: "Re: THOUSANDS of extra Resources added"
- Next in thread: Gary L. Chefetz \(MVP\): "Re: THOUSANDS of extra Resources added"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|
Loading