Errors publishing to Project Server 2003

From: PottsNet2 (PottsNet2_at_discussions.microsoft.com)
Date: 11/16/04


Date: Mon, 15 Nov 2004 19:26:02 -0800

Sorry in advance for the long post but wanted to provide as much info as
possible.
We have a W2k3 server hosting all components of Project Server as well as
Project
Pro for testing. Currently, when publishing from Project Pro, individual
projects are
listed in the PWA Projects list but give the "not published..." dialog when
any one is selected. The project(s) can be reopened, changed and saved by
Project Professional. The event log errors listed below are generated with
each attempt. I have deleted all testing projects (through PWA Admin) and
attempted to publish a *new* project from Project Pro to elliminate problems
with duplicate objects and corrupted project database entries. When the new
project is published, the Project Spooler icon in the system tray changes to
indicate that it is processing the XML file fed to it and the file gets
deleted from the folder. I have verified permissions for the ViewDrop folder
as well as the DSN attributes and site properties viewed through EditSite.
The last error listed is from the security event log and occurs at the same
time that the others start. The Local Service account had been given explicit
permissions to the registry key (and subkeys) listed but they seem to be lost
when the server is bounced.

Thanks in advance!

Event Type: Warning
Event Source: Microsoft Project Server Tracing Eventlog Provider
Event Category: None
Event ID: 1
Date: 11/15/2004
Time: 3:52:13 PM
User: NT AUTHORITY\LOCAL SERVICE
Computer: JOA006
Description:
Component: Views Notification Service
File: C:\Office\devsp\project\pcportal\source\viewsnotify\ViewNotify.cpp
Line: 207
Error Number: 0x800a0005
Description: <Description><![CDATA[View scheduler received error while
scheduling views]]></Description>
___________________________________

Component: PCSViews
File: ViewsDrop.cls
Line: -1
Error Number: 0x5
Description: <Description><![CDATA[Error Information: Invalid procedure call
or argument
Additional Information: An error occured processing the following view :-
<ViewsDropData><ProjectData><EntProjectName><![CDATA[ChkConn.Published]
]></EntProjectName><EntProjectID>4</EntProjectID></ProjectData><OrgGuid>projectserver</OrgGuid><ProjectID>105</ProjectID><BasePath>projectserver</BasePath><TimeStamp>2004-11-15T15:52:12</TimeStamp></ViewsDropData>
]]></Description>

-------------------------------------------------------------------------------------------------------------------------------------------

Event Type: Error
Event Source: Microsoft Project Server Tracing Eventlog Provider
Event Category: None
Event ID: 2
Date: 11/15/2004
Time: 3:52:13 PM
User: NT AUTHORITY\LOCAL SERVICE
Computer: JOA006
Description:
File: C:\Office\dev\project\WebClient\source\utility\pjadorsutil2.cpp
Line: 841
Error Number: 0x800a0cc1
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>
___________________________________

Component: ADODB.Recordset
Description: <Description><![CDATA[Item cannot be found in the collection
corresponding to the requested name or ordinal.]]></Description>

-------------------------------------------------------------------------------------------------------------------------------------------
Event Type: Error
Event Source: Microsoft Project Server Tracing Eventlog Provider
Event Category: None
Event ID: 2
Date: 11/15/2004
Time: 3:52:13 PM
User: NT AUTHORITY\LOCAL SERVICE
Computer: JOA006
Description:
Component: PjViewMgr
File: C:\Office\dev\project\WebClient\source\server\pjviewmgr\ViewCreator.cpp
Line: 1909
Error Number: 0x800a0cc1
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>

-------------------------------------------------------------------------------------------------------------------------------------------
Event Type: Error
Event Source: Microsoft Project Server Tracing Eventlog Provider
Event Category: None
Event ID: 2
Date: 11/15/2004
Time: 3:52:13 PM
User: NT AUTHORITY\LOCAL SERVICE
Computer: JOA006
Description:
Component: PjViewMgr
File: C:\Office\dev\project\WebClient\source\server\pjviewmgr\ViewCreator.cpp
Line: 1506
Error Number: 0x800a0cc1
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>

-------------------------------------------------------------------------------------------------------------------------------------------
Event Type: Error
Event Source: Microsoft Project Server Tracing Eventlog Provider
Event Category: None
Event ID: 2
Date: 11/15/2004
Time: 3:52:13 PM
User: NT AUTHORITY\LOCAL SERVICE
Computer: JOA006
Description:
Component: PjViewMgr
File: C:\Office\dev\project\WebClient\source\server\pjviewmgr\ViewCreator.cpp
Line: 1097
Error Number: 0x800a0cc1
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>

---------------------------------------------------------------------------------------------------------------------------------------------
Event Type: Error
Event Source: Microsoft Project Server Tracing Eventlog Provider
Event Category: None
Event ID: 2
Date: 11/15/2004
Time: 3:52:13 PM
User: NT AUTHORITY\LOCAL SERVICE
Computer: JOA006
Description:
Component: PjViewMgr
File: C:\Office\dev\project\WebClient\source\server\pjviewmgr\ViewCreator.cpp
Line: 1164
Error Number: 0x800a0cc1
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>

------------------------------------------------------------------------------------------------------------------------------------------
Event Type: Error
Event Source: Microsoft Project Server Tracing Eventlog Provider
Event Category: None
Event ID: 2
Date: 11/15/2004
Time: 3:52:13 PM
User: NT AUTHORITY\LOCAL SERVICE
Computer: JOA006
Description:
Component: PCSViews
File: ViewsDrop.cls
Line: -1
Error Number: 0x5
Description: <Description><![CDATA[Error Information: Invalid procedure call
or argument
Additional Information: An error occured processing the following view :-
<ViewsDropData><ProjectData><EntProjectName><![CDATA[ChkConn.Published]
]></EntProjectName><EntProjectID>4</EntProjectID></ProjectData><OrgGuid>projectserver</OrgGuid><ProjectID>105</ProjectID><BasePath>projectserver</BasePath><TimeStamp>2004-11-15T15:52:12</TimeStamp></ViewsDropData>
]]></Description>

------------------------------------------------------------------------------------------------------------------------------------------
Event Type: Warning
Event Source: Microsoft Project Server Tracing Eventlog Provider
Event Category: None
Event ID: 1
Date: 11/15/2004
Time: 3:52:13 PM
User: NT AUTHORITY\LOCAL SERVICE
Computer: JOA006
Description:
Component: Views Notification Service
File: C:\Office\devsp\project\pcportal\source\viewsnotify\ViewNotify.cpp
Line: 212
Error Number: 0x800a0005
Description: <Description><![CDATA[The views processor failed to process the
following document:

<ViewsDropData><ProjectData><EntProjectName><![CDATA[ChkConn.Published]
]></EntProjectName><EntProjectID>4</EntProjectID></ProjectData><OrgGuid>projectserver</OrgGuid><ProjectID>105</ProjectID><BasePath>projectserver</BasePath><TimeStamp>2004-11-15T15:52:12</TimeStamp></ViewsDropData>
]]></Description>

---------------------------------------------------------------------------------------------------------------------------------------------
Event Type: Failure Audit
Event Source: Security
Event Category: Object Access
Event ID: 560
Date: 11/15/2004
Time: 4:30:39 PM
User: NT AUTHORITY\LOCAL SERVICE
Computer: JOA006
Description:
Object Open:
         Object Server: Security
         Object Type: Key
         Object
Name: \REGISTRY\MACHINE\SOFTWARE\Description\Microsoft\Rpc\UuidTemporaryData
         Handle ID: -
         Operation ID: {0,755572}
         Process ID: 332
         Image File Name: C:\Program Files\Microsoft Office Project Server
2003\BIN\VWNOTIFY.EXE
         Primary User Name: LOCAL SERVICE
         Primary Domain: NT AUTHORITY
         Primary Logon ID: (0x0,0x3E5)
         Client User Name: -
         Client Domain: -
         Client Logon ID: -
         Accesses: Query key value
                        Set key value
                        
         Privileges: -
         Restricted Sid Count: 0
         Access Mask: 0x3

-- 
John


Relevant Pages

  • RE: Errors publishing to Project Server 2003
    ... > We have a W2k3 server hosting all components of Project Server as well as ... > Component: Views Notification Service ... > Component: PCSViews ... > Component: PjViewMgr ...
    (microsoft.public.project.pro_and_server)
  • Not able to see tasks details in Project Center view
    ... server running SQL and 1 server running sharepoint services thanks. ... Component: Views Notification Service ... An error occured processing the following view ... Component: PjViewMgr ...
    (microsoft.public.project.pro_and_server)
  • Re: View A Project details
    ... Everyone Full Control on the ViewDrop folder. ... We wrote the book on Project Server ... >>Notification Service is running under is failing. ... >>> - the above mentioned username has full permissions to ...
    (microsoft.public.project.pro_and_server)
  • Re: Olap Cube excessive processing time
    ... there is nothing else running on the project server at 1AM ... >large number of assignments. ... >Notification Service not running on a dedicated server, ...
    (microsoft.public.project.pro_and_server)
  • Re: Errors publishing to Project Server 2003
    ... Server 2003 and has the services running under the 'Local Service' ... needs to be assigned a 'Log On As' with an account that ... > The last error listed is from the security event log and occurs at the same ... > Component: PjViewMgr ...
    (microsoft.public.project.pro_and_server)