Re: How can i hide deleted tasks of administrative projects from PWA??

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance

From: Dale Howard [MVP] ("Dale)
Date: 10/14/04


Date: Thu, 14 Oct 2004 15:05:56 -0600


??? --

You cannot hide tasks in an administrative project. Instead, your Project
Server administrator should save the admin project as an .mpp file, delete
the project from the Project Server database, import the project back into
the system, and then republish the project. Hope this helps.

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"
"????????????" <administrator@hotmail.com> wrote in message 
news:5EF82BC1-C392-42E0-8F36-5C1542F1AB81@microsoft.com...
> When a task that belonges to administrative projects is deleted, how can i
> hide it from "my tasks" view in PWA?
> -- 
> ???????????? 


Relevant Pages

  • Re: Server 2002 admin projects
    ... We wrote the book on Project Server ... "Michelle" wrote in message ... >>> I have been trying to create an administrative project ... >>> I do not have sufficient permissions. ...
    (microsoft.public.project.pro_and_server)
  • Turn off notifications for Administrative Projects in PS2003
    ... when one person adds hours to an Administrative project in Project ... I understand that notifications can be set from the links on the Home ... I saw the articles in regard to Project Server 2002. ... Bill ...
    (microsoft.public.project.pro_and_server)
  • disable e-mail notification for administrative projects
    ... I am using Project 2003 Professional and Proj 2003 Server and have implemented the default administrative project. ... I have assigned all resources to each of the tasks in the administrative project with 0%. ...
    (microsoft.public.project.pro_and_server)
  • Re: MS Project Server - Administrative Plan issue - Can not close it out
    ... Regarding the use of the booking type, ... don't see how an admin plan would work for us. ... > If you want to remove the admin project entirely from the Project Server ...
    (microsoft.public.project.pro_and_server)
  • Re: Slow network connections to Project Server - My solution
    ... - Last saved date for server files is in the SQL ProjectServer DB Table ... - Last saved date in an open mpp file is ActiveProject.LastSaveDate ... Project Summary Task option's turned on. ... > download everything everynight I'm afaid it will take too long. ...
    (microsoft.public.project.pro_and_server)