Re: How can I change the working day ?

Tech-Archive recommends: Fix windows errors by optimizing your registry

From: Dale Howard [MVP] ("Dale)
Date: 09/03/04


Date: Thu, 2 Sep 2004 22:03:16 -0600

Abby --

You need to open the Enterprise Global before you can change or create
enterprise calendars. Click Tools - Enterprise Options - Open Enterprise
Global, then click Tools - Change Working Time. Hope this helps.

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"
"abby" <hhyin2002@hotmail.com> wrote in message 
news:55aa01c49162$5fb44a10$a301280a@phx.gbl...
> Dale&#65306;
> Thank you for your answers.
> Now I'm logging in with administrator permissions and
> administrators group is the only group I belong to.
> I check the set on the Server Configuration page in PWA,
> the Change Working Days feature is permit in the features
> grid.
>
> On the other hand, When I open the dialog box of the
> Change Working Days, in standard calendar Option, I can't
> change the working day. But I can set up a new calendar in
> this page, but I don't know how to apply this calendar to
> the project.
>
> Can you give me some suggestiones?
> Thanks a lot.
>
>
>>-----Original Message-----
>>Abby --
>>
>>If you are logging in with administrator permissions, it
> sounds like someone
>>has set the Change Working Days permission to Deny in one
> of the Groups to
>>which you belong.  If a permission is set to Deny in one
> of your Groups, and
>>is set to Allow in all of your other Groups, the Deny
> permission will always
>>"trump" the Allow permission.  Alternately, one of your
> Project Server
>>administrators may have set the Change Working Days
> feature to Deny in the
>>features grid found on the Server Configuration page in
> PWA.  Hope this
>>helps.
>>
>>-- 
>>Dale A. Howard [MVP]
>>Enterprise Project Trainer/Consultant
>>http://www.msprojectexperts.com
>>"We wrote the book on Project Server"
>>
> 


Relevant Pages

  • Re: Cant Update Resource Calendar
    ... Category Permission: Edit Enterprise Resource Data ... It turns out I'm the Project Server Administrator. ... "Reid McTaggart" wrote: ... You may have been permitted to change the resource's calendar in the ...
    (microsoft.public.project)
  • Re: Base Calendar showing exceptions
    ... please post your Project Server questions to the ... in PWA and then click the Enterprise Calendars link in the Enterprise Data ... From there you can edit the calendar as you wish. ... There are few exceptions that are listed. ...
    (microsoft.public.project)
  • Re: The calendar in Project 2003 is greyed out and I can make no c
    ... You cannot change the Standard calendar because it is an enterprise ... Only the Project Server administrator can change this calendar, ... Enterprise Options - Open Enterprise Global) in Microsoft Project ...
    (microsoft.public.project.pro_and_server)
  • Re: Cant Update Resource Calendar
    ... It turns out I'm the Project Server Administrator. ... looks like I turned off my own permission somewhere? ... You may have been permitted to change the resource's calendar in the ... the tasks on which the resource will work. ...
    (microsoft.public.project)
  • Re: Change de standard calendar for a enterpriese resource
    ... enterprise calendar for this purpose. ... Enterprise Project Trainer/Consultant ... "We wrote the book on Project Server" ... > assign a enterprise resource the calendar used is the enterprise ...
    (microsoft.public.project.pro_and_server)