Re: How can I change the working day ?
From: Dale Howard [MVP] ("Dale)
Date: 09/03/04
- Next message: Sumit: "Re: Indicator Icons for Deleted Projects"
- Previous message: Greg Horodeck: "Re: 2003 Admin Project Limitations????"
- In reply to: abby: "Re: How can I change the working day ?"
- Next in thread: K Treston: "Re: How can I change the working day ?"
- Messages sorted by: [ date ] [ thread ]
Date: Thu, 2 Sep 2004 22:03:16 -0600
Abby --
You need to open the Enterprise Global before you can change or create
enterprise calendars. Click Tools - Enterprise Options - Open Enterprise
Global, then click Tools - Change Working Time. Hope this helps.
-- Dale A. Howard [MVP] Enterprise Project Trainer/Consultant http://www.msprojectexperts.com "We wrote the book on Project Server" "abby" <hhyin2002@hotmail.com> wrote in message news:55aa01c49162$5fb44a10$a301280a@phx.gbl... > Dale: > Thank you for your answers. > Now I'm logging in with administrator permissions and > administrators group is the only group I belong to. > I check the set on the Server Configuration page in PWA, > the Change Working Days feature is permit in the features > grid. > > On the other hand, When I open the dialog box of the > Change Working Days, in standard calendar Option, I can't > change the working day. But I can set up a new calendar in > this page, but I don't know how to apply this calendar to > the project. > > Can you give me some suggestiones? > Thanks a lot. > > >>-----Original Message----- >>Abby -- >> >>If you are logging in with administrator permissions, it > sounds like someone >>has set the Change Working Days permission to Deny in one > of the Groups to >>which you belong. If a permission is set to Deny in one > of your Groups, and >>is set to Allow in all of your other Groups, the Deny > permission will always >>"trump" the Allow permission. Alternately, one of your > Project Server >>administrators may have set the Change Working Days > feature to Deny in the >>features grid found on the Server Configuration page in > PWA. Hope this >>helps. >> >>-- >>Dale A. Howard [MVP] >>Enterprise Project Trainer/Consultant >>http://www.msprojectexperts.com >>"We wrote the book on Project Server" >> >
- Next message: Sumit: "Re: Indicator Icons for Deleted Projects"
- Previous message: Greg Horodeck: "Re: 2003 Admin Project Limitations????"
- In reply to: abby: "Re: How can I change the working day ?"
- Next in thread: K Treston: "Re: How can I change the working day ?"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|