Alternate use of proposed resource
From: Greg Horodeck (greghoro_at_ameritech.net)
Date: 08/24/04
- Next message: Dale Howard [MVP]: "Re: Deletion of Resources in Enterprise Resource Pool"
- Previous message: Don: "Re: Deletion of Resources in Enterprise Resource Pool"
- Next in thread: dwolf: "Re: Alternate use of proposed resource"
- Reply: dwolf: "Re: Alternate use of proposed resource"
- Messages sorted by: [ date ] [ thread ]
Date: Mon, 23 Aug 2004 22:11:37 -0500
I have found that one can switch a resource from committed to proposed, even
if actual hours have been submitted. These actuals are preserved.
Since a project does not appear on a time*** when a resource is proposed,
I have come up with a couple of ideas to use this feature in an alternative
way.
First, many have asked, how do I close a project out and prevent people from
submitting time. Certainly locked down time periods can minimize this risk
along with dilligence by the PM, but why couldn't the PM switch all of the
resources to proposed after zero'ing out remaining hours? If you can't see
it, you can't report against it?
Also, we have a large organization and have many Administrative projects.
When a resource moves from one group to another in the organization and has
to be placed into a new Administrative project, wouldn't it be clean to
change them to proposed in the old one? Easier than asking the resource to
hide task.
Thoughts?
Greg
- Next message: Dale Howard [MVP]: "Re: Deletion of Resources in Enterprise Resource Pool"
- Previous message: Don: "Re: Deletion of Resources in Enterprise Resource Pool"
- Next in thread: dwolf: "Re: Alternate use of proposed resource"
- Reply: dwolf: "Re: Alternate use of proposed resource"
- Messages sorted by: [ date ] [ thread ]