Re: 2003 Admin Project Limitations????

From: Randy (Randy_at_discussions.microsoft.com)
Date: 08/19/04


Date: Thu, 19 Aug 2004 06:47:02 -0700

Dale,

Actually, I would prefer to have each team have their own admin project but
we are not sure the maturity level is where it needs to be yet (as far as
methodologies, work flow, etc...). I will revisit this.

Do admin projects have limitations as far as the number of resources and
tasks go?

Thanks!

Randy

"Dale Howard [MVP]" wrote:

> Randy --
>
> I would recommend that you seriously reconsider assigning all 800 resources
> to each task. I beieve that such a project would be an administrative
> nightmare to manage! Instead, I would recommend that you use an alternate
> approach, such as creating a separate administrative project for each team,
> department, business unit, or something like that. If you need to view the
> total information across all of the administrative projects, you could
> create a temporary master project containing each administrative project as
> a subproject. Just a thought.
>
> --
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> http://www.msprojectexperts.com
> "We wrote the book on Project Server"
>
>
> "Randy" <Randy@discussions.microsoft.com> wrote in message
> news:1D970822-600A-4BF0-BE6B-4D51649F67C4@microsoft.com...
> > I'm about to implement an Admin Project and was just told that you can
> only
> > assign 500 resources per project (for instance 50 resources on 10 tasks).
> I
> > have not found this documented anywhere and am looking for confirmation.
> I
> > was hoping to set up one admin project with approx. 8 tasks and assign all
> > 800 resources to each task. Any suggestions would be greatly appreciated.
> >
> > Thanks!
> >
> > Randy
>
>
>



Relevant Pages

  • Re: 2003 Admin Project Limitations????
    ... I would recommend that you seriously reconsider assigning all 800 resources ... "Randy" wrote in message ... > was hoping to set up one admin project with approx. ...
    (microsoft.public.project.pro_and_server)
  • Re: Removing a resource from a task with actuals
    ... It sounds like you are using an administrative project in an environment ... way to remove the resource in question is for your Project Server ... administrator to turn off Managed Time Periods temporarily. ... > I have an admin project in which I have user A assigned to several admin ...
    (microsoft.public.project.pro_and_server)
  • Re: Removing a resource from a task with actuals
    ... > Mauricio -- ... > It sounds like you are using an administrative project in an environment ... > way to remove the resource in question is for your Project Server ... >> I have an admin project in which I have user A assigned to several admin ...
    (microsoft.public.project.pro_and_server)
  • Stopping task update notifications on Administrative projects
    ... anyone know how to keep task notifications from being send ... Set up an Admin project with the various ... published as an Administrative project. ... update message gets sent to all users that the task has ...
    (microsoft.public.project.pro_and_server)
  • Re: How can i hide deleted tasks of administrative projects from PWA??
    ... You cannot hide tasks in an administrative project. ... Server administrator should save the admin project as an .mpp file, ...
    (microsoft.public.project.pro_and_server)