Re: 2003 Admin Project Limitations????
From: Randy (Randy_at_discussions.microsoft.com)
Date: 08/19/04
- Next message: Marc: "Re: General question"
- Previous message: Nick: "Migration from PS2002 to PS2003. Advice needed"
- In reply to: Dale Howard [MVP]: "Re: 2003 Admin Project Limitations????"
- Next in thread: Dale Howard [MVP]: "Re: 2003 Admin Project Limitations????"
- Reply: Dale Howard [MVP]: "Re: 2003 Admin Project Limitations????"
- Messages sorted by: [ date ] [ thread ]
Date: Thu, 19 Aug 2004 06:47:02 -0700
Dale,
Actually, I would prefer to have each team have their own admin project but
we are not sure the maturity level is where it needs to be yet (as far as
methodologies, work flow, etc...). I will revisit this.
Do admin projects have limitations as far as the number of resources and
tasks go?
Thanks!
Randy
"Dale Howard [MVP]" wrote:
> Randy --
>
> I would recommend that you seriously reconsider assigning all 800 resources
> to each task. I beieve that such a project would be an administrative
> nightmare to manage! Instead, I would recommend that you use an alternate
> approach, such as creating a separate administrative project for each team,
> department, business unit, or something like that. If you need to view the
> total information across all of the administrative projects, you could
> create a temporary master project containing each administrative project as
> a subproject. Just a thought.
>
> --
> Dale A. Howard [MVP]
> Enterprise Project Trainer/Consultant
> http://www.msprojectexperts.com
> "We wrote the book on Project Server"
>
>
> "Randy" <Randy@discussions.microsoft.com> wrote in message
> news:1D970822-600A-4BF0-BE6B-4D51649F67C4@microsoft.com...
> > I'm about to implement an Admin Project and was just told that you can
> only
> > assign 500 resources per project (for instance 50 resources on 10 tasks).
> I
> > have not found this documented anywhere and am looking for confirmation.
> I
> > was hoping to set up one admin project with approx. 8 tasks and assign all
> > 800 resources to each task. Any suggestions would be greatly appreciated.
> >
> > Thanks!
> >
> > Randy
>
>
>
- Next message: Marc: "Re: General question"
- Previous message: Nick: "Migration from PS2002 to PS2003. Advice needed"
- In reply to: Dale Howard [MVP]: "Re: 2003 Admin Project Limitations????"
- Next in thread: Dale Howard [MVP]: "Re: 2003 Admin Project Limitations????"
- Reply: Dale Howard [MVP]: "Re: 2003 Admin Project Limitations????"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|