Re: Adding actual hours when I extend duration
From: Gary L. Chefetz \(MVP\) ("Gary)
Date: 08/07/04
- Previous message: Gary L. Chefetz \(MVP\): "Re: Problem with Preoject Server 2003 SP1"
- In reply to: Greg Horodeck: "Adding actual hours when I extend duration"
- Messages sorted by: [ date ] [ thread ]
Date: Sat, 7 Aug 2004 14:17:22 -0400
Greg:
Completely normal behavior because the one resource is 100% complete,
extending the duration for that resource adds actual work rather than
remaining work unless you take control of all of the assignment parameters.
In a task view such as the Gantt chart, click Window > Split. Select the
task and add the hours to the resources as necessary in the appropriate
window.
-- Gary L. Chefetz, MVP "We wrote the book on Project Server http://www.msprojectexperts.com - "Greg Horodeck" <greghoro@ameritech.net> wrote in message news:#E7mu7CfEHA.3148@TK2MSFTNGP10.phx.gbl... > Situation: fixed duration task, several resources assigned to the task, one > is finished, the rest have remaining hours. > > When I extend the duration, the resources that are not complete have their > remaining hours incremented while the resource that was complete has their > actual hours incremented, remaining hours remains zero. > > I would expect that all resources should have their remaining hours > incremented and that the actual hours would not be affected. > > Can anyone explain the rationale behind this behavior? > > > Greg > >
- Previous message: Gary L. Chefetz \(MVP\): "Re: Problem with Preoject Server 2003 SP1"
- In reply to: Greg Horodeck: "Adding actual hours when I extend duration"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|