Re: Adding actual hours when I extend duration

From: Gary L. Chefetz \(MVP\) ("Gary)
Date: 08/07/04

  • Next message: Sisterfriend: "Address Template"
    Date: Sat, 7 Aug 2004 14:17:22 -0400
    
    

    Greg:

    Completely normal behavior because the one resource is 100% complete,
    extending the duration for that resource adds actual work rather than
    remaining work unless you take control of all of the assignment parameters.
    In a task view such as the Gantt chart, click Window > Split. Select the
    task and add the hours to the resources as necessary in the appropriate
    window.

    -- 
    Gary L. Chefetz, MVP
    "We wrote the book on Project Server
    http://www.msprojectexperts.com
    -
    "Greg Horodeck" <greghoro@ameritech.net> wrote in message
    news:#E7mu7CfEHA.3148@TK2MSFTNGP10.phx.gbl...
    > Situation: fixed duration task, several resources assigned to the task,
    one
    > is finished, the rest have remaining hours.
    >
    > When I extend the duration, the resources that are not complete have their
    > remaining hours incremented while the resource that was complete has their
    > actual hours incremented, remaining hours remains zero.
    >
    > I would expect that all resources should have their remaining hours
    > incremented and that the actual hours would not be affected.
    >
    > Can anyone explain the rationale behind this behavior?
    >
    >
    > Greg
    >
    >
    

  • Next message: Sisterfriend: "Address Template"

    Relevant Pages

    • Re: What should be put into a duration?
      ... the availability of the resources required to do the work. ... usually assign a resource at 100% - if Bob is assigned to wax widgets I'm ... So when I input the task I'm going to estimate its duration and let Project ... the training should be split out as individual tasks in their own ...
      (microsoft.public.project)
    • Re: Isnt there a "Machine" Resource Type???
      ... I may also have to go back and fix the duration ... The answer is there is only ONE CLASS used for allocated resources, ... Fixed units, fixed work, and fixed duration only applies to what happens ... SCHEDULE these d_mn tasks. ...
      (microsoft.public.project)
    • Re: Estimated dates
      ... Now your problem is figure out exactly HOW to achieve those objectives - what workflow organization and what sorts of resources and how many to assign where will be required in order for it to be possible for these tasks to take place where they must take place in order for your project to be successful. ... I have a set schedule that I need to stick to based on outside ... I can in fact think of tasks that could have a flexible duration - that could ... Than or a Finish No Earlier Than constraint date (bet you have a little ...
      (microsoft.public.project)
    • Re: Isnt there a "Machine" Resource Type???
      ... to resources on a task, I may also have to go back and fix the duration ... assignments" checkbox is turned OFF, ... by leveling when resources are overallocated) and suspensions (the ... Leveling never changes the amount of a resource's work nor the duration ...
      (microsoft.public.project)
    • Re: Isnt there a "Machine" Resource Type???
      ... I may also have to go back and fix the duration ... The answer is there is only ONE CLASS used for allocated resources, ... Fixed units, fixed work, and fixed duration only applies to what happens ... scheduling scenario and this post is getting more detailed than I have ...
      (microsoft.public.project)