Re: Collecting Actuals using Project Web Access

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance

From: Dale Howard [MVP] ("Dale)
Date: 07/22/04


Date: Thu, 22 Jul 2004 17:32:20 -0600

Tim --

You are not doing anything wrong; the software is performing as designed.
It sounds like you are using the "Actual work done and work remaining"
method of tracking progress in Project Server. When you use this method of
tracking and enter a value in the Actual Work column, Microsoft Project
evenly apportions the Actual Work across the life of the task in accordance
with the original Units assigned to the task. Therefore, since you assigned
a resource at 12 hours of Work across a 15-day Duration task, Microsoft set
the assignment at 10% Units or .8 hours of Work per day. When you enter 6
hours of Actual Work for the task in the Actual Work column in PWA, the
system applies the 6 hours of Actual Work at .8 hours per day for the first
7 days of the task and .4 hours on the 8th day. Thus, it applies 4 hours of
Actual Work during the first week and 2 hours of Actual Work during the
second week.

If this is not the behavior you wish, then I would recommend you use a
different tracking method that would better suit your needs. I believe a
more appropriate choice would be the "Hours of work done per day or per
week" method with the "Users should report their total hours worked for a
week" option. This would allow the resource to enter 6 hours of work for
the first week and have all 6 hours of Actual Work show up during the first
week only. Hope this explanation and recommendation helps.

-- 
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"
"Tim Ivey" <TimIvey@discussions.microsoft.com> wrote in message
news:5BE2618B-702E-4B33-A37E-390EB4482765@microsoft.com...
> I have to use Project Web Access to collect actual hours per tasks.
>
> So here is the senario.
> I have a task that is 3 weeks long and I plan on working 4 hours per week
>
> Problem.
> If I work 6 hours in the first week and enter this information through
PWA, The plan is updated with 4 actual hours in week 1 and 2 actual hours in
week too instead of placing all of the hours in week 1.
>
> Do I have a setting wrong.  Is this the design of this program.
>
> Any Help, Advice or Guidance is greatly appreciated


Relevant Pages

  • Re: speaker box assignment
    ... I'm studying industrial design at Wentworth Institute of Technology ... Re=3.5 Ohms ... P-Vd= 0.00684 Liters ... My assignment is to design two bookshelf / desktop speakers that not ...
    (sci.electronics.repair)
  • Re: Initialization of arrays
    ... you need the assignment pattern syntax with an ... and can therefore be more intelligent than concatenation ... on them to implement SV design constructs sooner rather ...
    (comp.arch.fpga)
  • Re: basic: should you reassign parameters, or use them without renaming/reassigning?
    ... to perform the assignment ... (change of this kind indicates a design change/bad design, ... > are declared in the method signature: ... > public void CreateNewsletter (int pubVol, int pubNo, string title, ...
    (microsoft.public.dotnet.languages.csharp)
  • Re: "Spy" on visitors
    ... Apart from the cool factor of a visual tracking system like this it is actually a very useful design ... > including the messages users sent to each other, why, because thats what the customer wanted. ...
    (microsoft.public.dotnet.framework.aspnet)
  • Re: Query with Rows from one table and columns from another (???)
    ... You are probably looking for a crosstab query. ... > well as query and sql and form design. ... > table for each assignment type with fields ... > for each assignment for each student. ...
    (microsoft.public.access.queries)