Re: Enterprise Resource Pool and SP1
From: George Haney III, PMP,CPM (haneygn_at_lilly.com)
Date: 05/17/04
- Next message: Brent99Admin: "RBS Creation Problem"
- Previous message: Gary L. Chefetz [MVP]: "Re: Project Server Database Connection Issues"
- In reply to: George Haney: "Enterprise Resource Pool and SP1"
- Next in thread: Jay: "Re: Enterprise Resource Pool and SP1"
- Reply: Jay: "Re: Enterprise Resource Pool and SP1"
- Messages sorted by: [ date ] [ thread ]
Date: 17 May 2004 11:20:54 -0700
FOUND IT!
What we did was
1. Uninstall Project 2002 Server
2. Update Windows Script Host - Restart
3. Re-install MDAC 2.8 - Restart
4. Re-Install XML 4.0 - restart
5. Reinstall/setup Project 2002 server using the attach to existing db
6. restart
After analysis of servers that were and servers that were not
experiencing the issue, we determined that the Windows File Protection
scheme was preventing many many files from being installed but the
install did not tell us!!!!!
So we installed then restarted each item.
All is well now.
George E. Haney III, PMP, CPM
george.haney@technologist.com
"George Haney" <haneygn@lilly.com> wrote in message news:<83a301c431fc$2cb16780$a101280a@phx.gbl>...
> I have the same issue and no word from MS....
>
> George E. Haney III, PMP,CPM
> george.haney@technologist.com
> >-----Original Message-----
> >I recently installed SP1 for Project Professional 2002 on
> my laptop now whenever I open a resource in the ERP I get
> the following error if I close the pool with without
> saving the changes. Even if I simply look at a resource
> with making any change at all it prompts me to save
> changes and when I say no i get the error.
> >"Project Server was unable to process the request.
> > An invalid node name parameter was specified."
> >If I actually make a change and try to save it I get an
> error box stating that one of the fields on the resources
> is incorrect, it always shows the Windows user name field
> and the Resource Name field. No matter how you change or
> update these fields the box will not clear out, you have
> to cancel the save and which point you get the first error
> (the error above) and then the resource is checked out.
> You must then got to PWA and check the resource back in.
> I can open and make changes to any resource from my other
> machine which has not been updated to Project Professional
> SP1. Any help on thise would appreciated. I haven't been
> able to find one word on Microsofts support site for this
> error.
> >
> >.
> >
- Next message: Brent99Admin: "RBS Creation Problem"
- Previous message: Gary L. Chefetz [MVP]: "Re: Project Server Database Connection Issues"
- In reply to: George Haney: "Enterprise Resource Pool and SP1"
- Next in thread: Jay: "Re: Enterprise Resource Pool and SP1"
- Reply: Jay: "Re: Enterprise Resource Pool and SP1"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|